Mexico’s renewable clampdown puts Neoen’s ultra-competitive PV plant in limbo

Facebook
Twitter
LinkedIn
Reddit
Email
Featuring 191MW of LONGi Solar’s mono-crystalline modules, El Llano is a 2017 auction winner and raised US$280m from banks in March 2019. Image credit: LONGi Solar

Operators are starting to feel the impacts of Mexico’s recent decision to block renewable project connections, with a major solar project paralysed weeks after coming online.

In recent days, Neoen revealed it is set to lose millions every month after its 375MWp El Llano solar PV installation was put on hold by power market operator CENACE, which moved earlier in May to block the compulsory grid tests for all renewable plants nationwide.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

El Llano – a complex featuring 191MW of LONGi Solar’s mono-crystalline modules – reached full deployment earlier at the start of 2020. Pending the pre-operational tests due before July, the 375MWp PV plant had already started pumping power into the grid, at tariffs below the US$19/MWh mark.

CENACE’s move to suspend such tests will, Neoen estimates, spark monthly EBITDA shortfall of US$2 million for the firm. The group said it “stands ready” to put the El Llano power plant back into service and resume testing as soon as CENACE’s block is lifted.

CENACE, an agency owned by the Mexican state, justified its move earlier this month by arguing that “intermittent” wind and PV plants could hinder grid-wide stability at a time when the country is battling COVID-19. Renewable bodies have rejected the claim and flagged the impacts (see table below) they believe the blocking of pre-operational tests will entail.

The renewable pipeline affected by CENACE’s crackdown

ALREADY FINISHED PV AND WIND PLANTS PV AND WIND PLANTS UNDER CONSTRUCTION CO2 SAVINGS MEXICO MAY MISS
28 plants, 3.2GW 16 plants, 2.06GW 714,945 tonnes per month
JOBS AT RISK DIRECT INVESTMENT AT RISK NUMBER OF STATES AFFECTED
29,517 US$6.42 billion 18
Source: Asolmex, Amdee

In recent days, green energy associations including Asolmex (solar) and Amdee (wind) put forward a statement mapping out the renewable projects they claimed have been brought to a standstill by CENACE’s crackdown.

The multi-billion-US-dollar, multi-gigawatt fleet of 44 stranded solar and wind assets spans nearly 20 states (see table below), and features both projects ready to go live and those still progressing through construction.

The controversy pitting green energy players against the government of Andrés Manuel López Obrador may yet reach the courts. The possibility was openly discussed by Mexican business council the CCE last week, when it said it will “take the necessary legal measures” against CENACE’s decision, in a bid to “preserve the level field and Mexicans' right to a healthy environment.”

Earlier court showdowns with the renewables industry have ended in a setback for the Mexican president. His government’s attempt to award clean energy certificates meant for post-2014 renewable projects to legacy hydro and nuclear plants was overturned by a judge late December.

Geographic breakdown of stranded solar and wind assets: Top states

Already finished projects: Sonora (2 projects, 474MW), Aguascalientes (2 projects, 400MW), Coahuila (3 projects, 348MW)

Under-construction projects: Yucatán (3 projects, 390MW), Jalisco (2 projects, 334 MW), Tamaulipas (2 projects, 315MW)

Source: Asolmex, Amdee

Despite those and other renewables-unfriendly moves since López Obrador took power in 2018 – such as auction cancellations and the reopening of old PPAs – Mexican solar has witnessed rapid growth in recent months, with cumulative PV installs booming from 2018 (3GW) to 2019 (5GW).

Caught in the latest crossfire, Neoen’s El Llano is a winner of Mexico’s green energy auction of late 2017. In March 2019, the 375MWp plant in the state of Aguascalientes lined up financing of US$280 million from top banks, including Bancomext, Natixis and Société Générale.

Neoen’s work in Mexico is part of a busy solar construction pipeline elsewhere in Latin America. Projects of note include a complex mixing PV (143MWp) and li-ion batteries (3MW/1.8MWh) in El Salvador and the 208MWp Altiplano solar project, both due to complete this year.

PV Tech has set up a dedicated tracker to map out how the COVID-19 pandemic is disrupting solar supply chains worldwide. You can read the latest updates here.

If you have a COVID-19 statement to share or a story on how the pandemic is disrupting a solar business anywhere in the world, do get in touch at [email protected] or [email protected].