Operations at REC Moses Lake are short-lived as more problems arise

REC Silicon’s Silicon III plant at Moses Lake, Washington has met with further delays, following concerns for “process safety reasons” during the ramp-up. The plant had run successfully for 10 days prior to the decision being made to stop production as a result of instabilities in operating parameters.

The news comes less than a week after the company announced that the initial ramp phase had begun. The company reiterated its statement prior to the ramp-up that interruptions are to be expected during such an operation.

A Reuters report on the news quoted new CEO Ole Enger as saying that it was "impossible to be precise" on how long the shutdown would last, and that it was "perfectly normal" to have problems in this early phase of such plants. Simulations of real data have to be carried out and analyzed before the plant can resume production.

The company will provide an update on progress during the presentation of the Q1 2009 financial report on April 29, 2009.

Newsletter

Preview Latest Subscribe
We won't share your details - promise!

Publications

  • Photovoltaics International 16th Edition

    Photovoltaics International 16th Edition

    This sixteenth edition of Photovoltaics International marks four years of production of the quarterly journal. As always, our focus is on efficiency and quality improvement and cost reduction in manufacturing. As 2012 rolls along, companies are falling by the wayside due to supply and demand issues, ASP declines and drastic governmental subsidy cuts. A clear picture of 2012 is offered through papers from the likes of TÜV Rheinland, Fraunhofer ISE, SEMI PV Group and EPIA, amongst others.

  • Photovoltaics International Lite, Volume 05 - 2011

    Photovoltaics International Lite, Volume 05 - 2011

    This digital interactive Lite sees Tom Cheyney follow Agua Caliente’s progress on becoming one of first truly utility-scale PV power farms, where 40–50MW (AC) will be commissioned by the end of the year. We also feature one of the world’s largest silicon thin-film PV power plants, Avenal; a report on warnings of the collapse of module prices from Solarbuzz and PI-Berlin presents tips on PV module testing. A print version of this edition will be distributed at Solar Power International 2011 in Dallas, Texas.

  • Manufacturing The Solar Future: The 2012 Production Annual

    Manufacturing The Solar Future: The 2012 Production Annual

    Manufacturing the Solar Future 2012, the second in the Photovoltaics International PV Production Annual series, delivers the next installment of in-depth technical manufacturing information on PV production processes.

Partners

Acknowledgements

Solar Media