Parabel finalizes design for 100MW solar park in Germany

  • The Marienfliess Solar Cluster is to be constructed in several phases, to begin at the end of this month, on 430 hectares of land, with completion expected in 2013.
    The Marienfliess Solar Cluster is to be constructed in several phases, to begin at the end of this month, on 430 hectares of land, with completion expected in 2013.

Initiated this time last year, Parabel has now finalized the design for the 100MW solar park on parts of the former Jännersdorf military training area in Prignitz, Brandenburg, Germany. The Marienfliess Solar Cluster is to be constructed in several phases, to begin at the end of this month, on 430 hectares of land, with completion expected in 2013. There will be four construction sites near Jännersdorf and further east, two sites in Krempendorf.

“The approval procedure has been a rather protracted process. The requirements for the compensatory and supplementary measures were very high, so we had to readjust the project design,” according to Jürgen Will, CEO of Parabel AG. “With the shape of the clusters that has now been attained, we have not only met all ecological requirements but have also managed to organically integrate the individual solar arrays into the landscape. In addition, the local community and environment will now benefit from newly created public paths, the planting of valuable mixed forest areas instead of the existing monocultures, and the designation of new biotopes.”

Due to the previous military purpose of the area, it will need to be cleared of munitions since the site is contaminated with munitions fragments. The environmental and species conservation measures include the resettlement of sand lizards. These and other measures will be organised and conducted by Parabel AG in dialogue with environmental conservation organisations.

Parabel states that the municipal federation of Meyenburg, to which the Marienfliess municipality belongs, is well on the way to becoming one of the most important renewable energy regions in Germany, with the first wind turbine in Brandenburg installed in 1991. The new solar power generation is hoped to enable further local business taxes to flow into the Marienfliess municipality.
 

Post a Comment

Post

Newsletter

Preview Latest Subscribe
We won't share your details - promise!

Publications

  • Photovoltaics International 16th Edition

    Photovoltaics International 16th Edition

    This sixteenth edition of Photovoltaics International marks four years of production of the quarterly journal. As always, our focus is on efficiency and quality improvement and cost reduction in manufacturing. As 2012 rolls along, companies are falling by the wayside due to supply and demand issues, ASP declines and drastic governmental subsidy cuts. A clear picture of 2012 is offered through papers from the likes of TÜV Rheinland, Fraunhofer ISE, SEMI PV Group and EPIA, amongst others.

  • Photovoltaics International Lite, Volume 05 - 2011

    Photovoltaics International Lite, Volume 05 - 2011

    This digital interactive Lite sees Tom Cheyney follow Agua Caliente’s progress on becoming one of first truly utility-scale PV power farms, where 40–50MW (AC) will be commissioned by the end of the year. We also feature one of the world’s largest silicon thin-film PV power plants, Avenal; a report on warnings of the collapse of module prices from Solarbuzz and PI-Berlin presents tips on PV module testing. A print version of this edition will be distributed at Solar Power International 2011 in Dallas, Texas.

  • Manufacturing The Solar Future: The 2012 Production Annual

    Manufacturing The Solar Future: The 2012 Production Annual

    Manufacturing the Solar Future 2012, the second in the Photovoltaics International PV Production Annual series, delivers the next installment of in-depth technical manufacturing information on PV production processes.

Partners

Acknowledgements

Solar Media