Conergy expects Frankfurt (Oder) fab to be at full capacity by 2H09

14 April 2008 - Solar Cell - News

Conergy has said that its initial ramp of its new €250 million integrated solar cell fab in Frankfurt (Oder), Germany, now has approximately 90 percent of the production tools installed and is qualified for production.

The plan includes limited production in the current quarter due to material supply bottlenecks, but silicon supplier MEMC is expected to start greater levels of supply starting in July, 2008 and to meet the growing production requirements of partial capacity utilization in 2008, the company said.

MEMC is also expected to supply sufficient silicon quantities for Conergy to reach full solar cell module capacity of 250MW from the second half of 2009.

 

Reader Comments
No comments yet!
Add your comment
Your name:
Your email: Not to worry, email address will not be published.
Please enter the word you see in the image below (or click the speaker icon to hear it):
 Click here to hear the word