Officials from Hokkaido Electric Power in Japan are being forced to review applications made by large-scale PV developers due to fears these installations could exceed the grid’s capacity.
Utility Hokkaido Electric Power explained to applicants that projects over 2MW cannot be added to the grid, Satoshi Takada, a spokesman for the utility, said in an interview with Bloomberg.
Unlock unlimited access for 12 whole months of distinctive global analysis
Photovoltaics International is now included.
- Regular insight and analysis of the industry’s biggest developments
- In-depth interviews with the industry’s leading figures
- Unlimited digital access to the PV Tech Power journal catalogue
- Unlimited digital access to the Photovoltaics International journal catalogue
- Access to more than 1,000 technical papers
- Discounts on Solar Media’s portfolio of events, in-person and virtual
Or continue reading this article for free
The attraction of Hokkaido is the availability and inexpensive cost of land in the region.
By the end of March, applications for grid connections totalled 1,568MW for plants of 2MW or larger, according to an April 17 statement from the utility, which said it had capacity for only 400MW.
As one response, Japan’s Ministry of Economy, Trade and Industry (METI) announced in April plans to install the world’s largest battery at an electrical substation in the prefecture of Hokkaido with an expected storage capacity of around 60MWh, and to be set up by March 2015.