SunEdison bankruptcy risk won’t derail Indian solar targets, says government

Facebook
Twitter
LinkedIn
Reddit
Email
MNRE joint secretary brushed off the impacts of a potential SunEdison bankruptcy on India's solar plans. Credit: Intersolar

The financial woes of US developer SunEdison would only have a small impact on India’s overall solar deployment targets and any incomplete PV projects would be retendered immediately, Tarun Kapoor, joint secretary of India’s Ministry of New and Renewable Energy (MNRE) has told PV Tech.

Embattled SunEdison has hit headlines of late after its yieldco subsidiary Terraform Global claimed that SunEdison is close to seeking bankruptcy protection. Terraform Global also sued SunEdison over alleged misappropriation of US$231 million funding that had been earmarked to complete solar projects in India.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

A source familiar with the matter told PV Tech that much of SunEdison’s solar pipeline in India is expected to go ahead as financing has been closed, however, the 500MW project in Andhra Pradesh and the 150MW project in Jharkhand, both won since last November, would be affected if SunEdison’s financial woes continued.

Kapoor said that if another company takes over SunEdison or it is able to raise money, then it could complete the projects, however, its well-publicised financial problems suggest that it will struggle to get lending from banks and reach financial closure for the projects.

Meanwhile, prospects for the 500MW Andhra Pradesh project may be hampered by it being won with an aggressively low tariff of INR4.63/kWh (US$0.07).

Earlier this week, however, reports emerged that Indian conglomerate Adani Group is considering buying SunEdison’s Indian assets.

When asked whether MNRE could be flexible in its solar auction rules, which mandate the original bidders to complete the projects themselves, Kapoor explained that MNRE already had some provisions for bank guarantees and for checking the networks of organisations looking to enter bids.

He added: “In this case, this organisation had a good network, but now it has gone down. These kinds of things cannot be foreseen and they do happen and, in case they are not able to build the project, then immediately we will retender, but they will lose their bank guarantee.

“We have some targets and we want the projects to come up. That is our challenge at the moment.”

Kapoor also said that were SunEdison to fail to complete its Indian projects, it would only be a “slight setback” on India’s overall solar pipeline explaining that MNRE tends to bid out slightly more capacity than its targets, to account for any doubtful projects. Meanwhile, MNRE itself will not lose any money and it will only be the developer that sees a financial loss.

Kapoor added: “We will ensure that it doesn’t create too much trouble for us as far as our targets are concerned.”

According to the 'India Solar Map 2015' from consultancy firm Bridge to India, as of last September, SunEdison had more than 700MW of Indian solar projects commissioned or in its pipeline. The Andhra Pradesh and Jharkhand projects have since been added.

This article has been revised to include comment from a source familiar with the matter.

Read Next

June 2, 2025
Arctech has partnered with ACME Cleantech Solutions to provide 175MW worth of solar trackers for an upcoming facility in Duqm, Oman.
May 30, 2025
Waaree Solar Americas – a subsidiary of Indian solar manufacturer Waaree Energies – has signed a 586MW solar module supply agreement with an undisclosed independent power producer (IPP).
May 29, 2025
Singapore-based engineering firm Sembcorp has received a letter of award from Indian public sector power company SJVN for 150MW of solar power and a 300MWh battery energy storage system (BESS).
Premium
May 29, 2025
PV Talk: Global Solar Council CEO Sonia Dunlop tells Shreeyashi Ojha why the solar industry needs collective action to combat political and supply-chain disruption.
May 28, 2025
The expansion is 100% compliant with the Indian government's requirement of Bureau of Indian Standards (BIS).
May 27, 2025
India has shipped 12.5GW of module capacity in the first quarter of 2025, according to data from energy consultancy JMK Research.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
June 17, 2025
Napa, USA
Upcoming Webinars
June 30, 2025
10am PST / 6pm BST
Solar Media Events
July 1, 2025
London, UK
Solar Media Events
July 1, 2025
London, UK
Solar Media Events
July 8, 2025
Asia