Spain’s renewables industry has lost €140 million (US$154 million) in revenue since the April 2025 grid blackout, according to Wood Mackenzie analysis.
Since the blackout, curtailment of renewables has remained elevated and is expected to worsen in the future as nearly 10GW of utility-scale solar connects in the fourth quarter of 2026 and through 2028.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
According to Wood Mackenzie, redispatch volumes in the technical constraints market have not returned to pre-blackout levels. Uncompensated constrained-off volumes now stand at 4% of available renewable energy supply so far this year, dominated by gas being called on to replace solar PV and wind generation being switched off to manage grid stability.
In certain nodes in Extremadura – central-eastern Spain – and Murcia – southwestern Spain – grid curtailment is already exceeding 25% of renewables output.
“Redispatch volumes in Spain’s constraints market have not normalised since the April 2025 blackout, and the numbers explain why,” said Agustin Huerga, research analyst, European Power and Renewables at Wood Mackenzie.
However, nearly half of the technical curtailment of renewables in 2026 was not due to physical constraints but to synchronous system issues: inertia, short-circuit current, and frequency and voltage control.
These are services that gas and nuclear power plants can provide, and for which a large portion of inverter-based solar and wind assets must be specifically configured to replicate; a large portion of Spain’s existing fleet is not yet set up in this way.
Nearly 7GW of solar PV and 26GW of wind power capacity require inverter retrofits to provide voltage control, half of which cannot provide this service without further investment.
“More than 35GW of the existing fleet can provide dynamic voltage control at no additional cost. Whether curtailment stabilises in 2027 or continues rising depends almost entirely on how fast that capacity is brought to compliance,” added Huerga.
If not a single gigawatt of that 35GW existing fleet mentioned by Huerga is brought to compliance, it could further increase renewables curtailment by 18% over two years and reach 6.5TWh by 2028. In 2023, that number was at 1.3TWh.
Solar-driven grid stress is concentrating geographically around Madrid, Toledo and Cáceres as 3GW of new solar PV comes online in those corridors. Developers are already responding, siting new projects in lower-resource zones including León, Valladolid, Huesca and Zaragoza, a sign that the investment geography of Spanish solar is shifting in real time.
Battery storage as a short-term solution
Wood Mackenzie explained that even though grid reinforcement is the structural solution, a seven-year average lead time from greenfield to completion rules it out as a near-term solution.
In the short term, battery storage and rising electricity demand are the solutions. Wood Mackenzie forecasts 10GW of battery storage operational by 2030. More than 40GW of battery storage is currently under development, and 25GW of that pipeline has already secured grid access approval.
Demand growth from data centres adds 2.3GW to the pipeline, of which 2GW is forecast to be operational by 2030.