Chinese solar PV manufacturer LONGi will supply 176MWdc of its Hi-MO 9 back contact (BC) solar modules to independent power producer (IPP) OX2’s Muswellbrook solar-plus-storage project at a former coal mine in New South Wales (NSW), Australia.
The project combines a 135MWac solar PV plant with battery storage in the Upper Hunter region. It is one of a growing number of Australian projects that reuse land once tied to coal mining for renewable energy generation.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
According to LONGi, around 300,000 Hi-MO 9 modules will be installed across the 482-hectare site. The company estimates that the solar PV plant will generate about 347GWh of electricity a year.
LONGi did not disclose the value of the supply agreement or the timing of module deliveries.
A joint venture between Bouygues Construction Australia and Equans Solar & Storage, both part of the French conglomerate Bouygues group, is leading the solar PV engineering, procurement and construction (EPC) work.
“The Muswellbrook Solar Farm is a prime example of sustainable land rehabilitation,” said Leon Zhang, president of utility Europe at LONGi.
He added that the company’s BC technology is designed to deliver energy yield and long-term value “even in challenging environments”.
From coal mine to solar-plus-storage
Swedish IPP OX2, owned by private equity firm EQT, started construction work at the project in May 2026. It expects to complete construction in 2028.
The site is in the Hunter-Central Coast Renewable Energy Zone (REZ). Most of the land is owned by a subsidiary of mine operator Idemitsu Australia, which worked with OX2 on developing the project after the Muswellbrook Coal Mine ceased operations in 2022.
The storage component differs across announcements. LONGi’s release describes a 100MWh battery storage system, while OX2’s construction announcement covered a 100MW/300MWh system, as reported by Energy-Storage.news.
OX2 has signed an offtake agreement for both the solar and battery storage components with an international offtaker, which it has not named. Japanese bank MUFG led the project financing.
The project reached its final regulatory step in August 2025, when OX2 secured approval under the Environment Protection and Biodiversity Conservation (EPBC) Act. At the time, Catherine Way, director of development at OX2 Australia, described it as “a leading example of the transition of the Upper Hunter Valley from coal mining to innovative post-mining land uses”.
It will connect to the National Electricity Market (NEM) through around 2.4km of new overhead lines tied into an existing 132kV line owned by Ausgrid. OX2 also secured EPBC approval for its 90MW Summerville solar-plus-storage project in NSW in July 2025.
LONGi said the Hi-MO 9 modules use its HPBC 2.0 cell technology, with module efficiencies of up to 24.8% and a temperature coefficient of -0.26%/°C. The company claims the modules have lower annual degradation than standard n-type products and are backed by a 30-year power warranty.
The supply deal follows LONGi’s push into the Australian market this month. At All-Energy Australia 2026 in Melbourne, the company launched two new BC modules and described Australia as “the most valuable market” for the company.
Executives told PV Tech that LONGi aims to compete with TOPCon in Australia’s utility-scale segment and to sell integrated solar PV and battery storage systems.