Indian committee to settle renewable energy disputes with NTPC, SECI

Facebook
Twitter
LinkedIn
Reddit
Email
Requests for timeline extensions are a key point of conflict. Credit: NTPC

India’s Ministry of New and Renewable Energy (MNRE) is setting up a committee to help resolve disputes between solar or wind developers and the two major state-run off-takers. 

The Dispute Resolution Mechanism would be applicable to unforeseen disputes that are either in or outside contractual agreements between renewable energy developers and the Solar Energy Corporation of India (SECI) or the utility National Thermal Power Corporation (NTPC). 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In a published Order, MNRE said that the Indian solar and wind sectors have been requesting such a mechanism for a long time. The ministry now aims to set up a transparent and unbiased mechanism, that includes a three-person independent Dispute Resolution Committee (DRC). This Committee will be based in Delhi and the selection of its members will be made in a manner that ensures no conflict of interest. It will apply to all programmes being implemented by SECI and NTPC. 

Meetings of the DRC shall be organized in the premises of SECI and NTPC respectively. No lawyers will be allowed when the parties present any case before the Committee. 

Cases to be considered by the DRC could include: 

  • Appeals against decisions given by SECI or NTPC on time extension requests based on terms within the contract. This includes requests for extensions due to 'Force Majeure' events like flooding and earthquakes, or delay in handing over of land by solar park developers and delay in connectivity, for example. If applications for extensions are made within the time limit of the contractual agreement, the developer, if unsatisfied with the decision of NTPC or SECI, can appeal to the DRC. 
  • Requests for extensions due to unforeseen circumstances not covered under the terms of the contract. This includes instances where the site is to be procured by the developer but there is a delay in land allotment due to policy change or registration by the government, or delays in grant of proposed connectivity due to court stays. 

DRC recommendations along with MNRE's observations will be placed before the Minister for New and Renewable Energy for a final decision.  

Further details on the Dispute Resolution Mechanism can be found here

Read Next

July 22, 2026
MNRE's eighth ALMM List-II revision expands Fujiyama Power's PV cell capacity and adds Avaada Electro as a new entrant.
Premium
July 21, 2026
'Home market strength plus Middle Eastern demand' has driven a surge in solar PV capacity in India, according to RenewAtlas and Wiki-Solar.
July 20, 2026
India's renewable energy ministry has extended the exemption from the ALMM List-II on PV cells for net-metering and open-access solar projects until the end of December 2026.
July 16, 2026
Alpex Solar expects commercial production to begin in August 2026 at its 2.2 GW TOPCon G12R solar cell facility in Kosi Kotwan, Mathura, UP.
July 15, 2026
Bluebird Solar has secured a 439.35 MW order from Indian state-owned power producer NTPC Renewable Energy Limited (NTPC REL).
July 15, 2026
CERC issues suo motu order to release interstate transmission connectivity reserved for renewable projects that failed to secure PPAs.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye