Puerto Rico introduces mandate for energy storage in new renewable projects

Facebook
Twitter
LinkedIn
Reddit
Email

Government-owned Puerto Rican electric power company Autoridad de Energia Electrica (AEE) has made it mandatory for developers of renewable energy projects to incorporate energy storage into new installations.

The new Minimum Technical Requirement (MTR) regulations have been introduced with the aim of minimising the impact of adding extra renewable energy capacity to the grid and reducing the level of infrastructure investment required to accommodate it.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Under new regulations, operators of renewable energy projects will be required to add 30% of the installation’s rated capacity in storage to aid frequency control, as well as the flexibility to keep 45% of the project’s capacity in reserve for at least one minute for ramping control to compensate for fluctuations in generated power from variable sources.

According to AEE executive director John F Alicea Flores, the company, which has a national monopoly on electricity generation, transmission and distribution through the grid and serves as regulator, recently completed a series of evaluations to find a realistic level of compliance that developers could meet.

In order to lower electricity prices for ratepayers and to make it easier to add new sources of electricity generated by renewable projects including PV, the Caribbean island territory’s government announced in October that it would begin renegotiating power purchase agreements (PPA) with project developers. According to Flores, negotiations are ongoing and AEE hopes to find “fair prices for all parties”. If negotiations are successful as expected, AEE will agree to purchase electricity from a number of renewable projects. Project proposals have been submitted from 64 developers, of which 15 are in the process of negotiating PPAs under the new MTR standards, according to local news sources.

In January 2014, the government of Puerto Rico will launch a new drive to procure 600MW of renewable energy capacity with the aim of adding that amount by the end of next year. This would represent an increase of 5% of energy generated from renewables in the Puerto Rican national energy mix, from 1% at present, to 6%.

Additionally, Puerto Rican authorities have also announced that proposed renewable energy projects on ‘sensitive’ or agricultural lands will be rejected.

To date, although energy storage has been recognised as a possible solution to providing adequate frequency control and ramping control to electricity transmission and distribution infrastructures, only authorities in California, via a storage requirement for utilities, Germany, via a subsidy on storage systems payable to residential users and Japan, through experiments in large-scale battery storage, have introduced policy measures aimed at adding energy storage to networks.

Read Next

Premium
August 14, 2025
SolMicroGrid has launched an Energy-as-a-Service (EaaS) partner program for project developers, engineering, procurement, and construction (EPC) companies and original equipment manufacturers (OEMs).
Premium
August 14, 2025
JP Casey investigates efforts currently being made to standardise the offtake agreement for the renewable power sector.
August 14, 2025
Germany’s federal energy network has awarded 2,271MW of PV capacity in its latest auction for ground-mounted and non-building solar projects.
August 14, 2025
The World Bank has approved a loan and investment worth up to US$250 million for United Solar’s planned polysilicon production plant in Oman.
August 14, 2025
South Africa’s state-owned energy utility, Eskom, has issued a request for proposals for 291MW of solar capacity.
August 14, 2025
Cells and wafers have accounted for 22% and 20%, respectively, of China’s product exports in the first half of 2025, according to Ember.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines