Gehrlicher Solar completes Perleberg solar park

  •   Gehrlicher Solar's 35MW Perleberg solar park. Image: Gehrlicher
    Gehrlicher Solar's 35MW Perleberg solar park. Image: Gehrlicher

Two and a half months after starting construction, Gehrlicher Solar advised that it has completed its Perleberg solar park, located between Hamburg and Berlin. The system holds a 35MWp nominal capacity and is anticipated to generate nearly 33 million kWh of power per year. The company noted that because of the solar park’s high capacity, it also built a separate expandable 110kV transformer station, which connected the solar installation to the grid on August 23.

“We are especially grateful to the policy makers at the City of Perleberg and District of Prignitz as well as the authorities in charge, such as the Perleberg building authority. In addition, we would also like to thank the two former property owners, the Brandenburg Land Association for Land Use and Management (Brandenburgische Boden Gesellschaft für Grundstücksverwaltung und -verwertung mbH (BBG)) and the Federal Agency for Real Estate Management (Bundesanstalt für Immobilienaufgaben (BImA)), as well as the Aero-Club Perleberg for their excellent cooperation at all times", commented Klaus Gehrlicher, CEO of Gehrlicher Solar AG.

The Perleberg solar park was built across 90 hectares on the site of a former military airport. Yingli supplied 144,144 of its modules, while 39 inverters were delivered by SMA. City and district officials plan to hold an official dedication ceremony for the project in mid-October.

Newsletter

Preview Latest
Subscribe
We won't share your details - promise!

Publications

  • Photovoltaics International 19th Edition

    For manufacturers who had their heads in the bunker during 2012, fighting falling ASPs and eroding margins, the nineteenth edition brings you details of what lies in store for this coming year. Wright Williams & Kelly return in this issue with their popular analysis of payback on technology buys; crucially they analyze n-type wafers, Al2O3 passivation and copper metallization. SERIS shows us how to achieve 18.7% efficiencies using low-cost etching techniques on diffused wafers. We also have two important technology roundups: CIGS from Helmholtz Berlin, and PV module encapsulation techniques from Fraunhofer ISE.

  • Manufacturing The Solar Future: The 2013 Production Annual

    In the ever-changing global solar markets, cost reduction and measures to increase cell efficiencies are the key tools available to PV manufacturers to create new opportunities and drive your business to the next level. Manufacturing the Solar Future 2013 is the third in the Photovoltaics International PV Production Annual series, delivering the next instalment of in-depth technical manufacturing information on PV production processes designed to help you gain the competitive edge.

Partners

Acknowledgements

Solar Media