Quality control issues delay commissioning at REC Moses Lake plant, production pushed out

December 16, 2008
Facebook
Twitter
LinkedIn
Reddit
Email

REC has updated the status of its polysilicon expansion at Plant III, saying it has formally accepted and taken control over the entire fluidized bed reactor (FBR) area and all related equipment at the new factory under construction in Moses Lake, WA.

While the first reactor test runs have been successfully completed, the company cautions that during final stages of the commissioning in the silane gas production area, quality issues were encountered with certain standard prefabricated carbon steel pipes. Control measures and repairs were begun immediately.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Based on the final conclusions of the analysis undertaken during the last few days, start-up of the silane production will be delayed until late January 2009, the company says. This will negatively affect production of polysilicon and, to some extent, wafers and solar cells in 2008 and early 2009.
 
In discussing the quality concerns related to the prefabricated carbon steel pipe welds in the silane gas section, the company says that its inspections revealed that the level of weld defects is above industry standard, and the quality falls outside the guaranteed standard delivery specifications for such “off-the-shelf” pipes.

All defective pipes have been supplied by one particular fabricator with a “seal of approval.” The supplier has taken full responsibility and has agreed to cover costs related to necessary weld repairs to ensure a safe start-up.
 
REC says that it has, together with Fluor and a third-party engineering firm, spent the last few days finalizing the analysis of the issue. Based on the current weld repair rate and the conclusion of the analysis, the start-up of commercial production has been moved to the end of January 2009. Aside from the weld repairs, the construction of the plant is complete.
 
“As a responsible producer we have a rigorous mechanical integrity program which allowed us to discover the defective workmanship,” explained Erik Thorsen, REC’s president/CEO. “The delay is obviously very unfortunate given our tight polysilicon situation, and we are working hard to mitigate and limit consequences as much as possible.” 

Simultaneously, start-up activities continue in the FBR section of the plant. Last week, the first two reactors were started on inert gas. This confirms that control systems and reactor characteristics are working in line with expectations. Next week, REC says it intends to start running full tests of the FBR reactors on silane gas from existing plants.
 
“As we have taken over the FBR-section of the plant, we will continue to prepare for start-up of commercial production and the coming ramp-up period in parallel with the ongoing weld repairs,” Thorsen says. “We remain comfortable with FBR from a technology perspective and its low-cost and high-quality capabilities. However, there is always risks related to starting up new technology.”
 
Plant III was previously scheduled to produce up to 400 metric tons of polysilicon by the end of 2008. Given an expected start-up of commercial production toward the end of January 2009, this year’s production will be reduced to only minor test volumes, according to REC.

For 2009, the production is expected to be about 5000 metric tons; the plant is designed to handle a 6500-metric ton annual production capacity of 6,500 MT.

Read Next

Premium
November 7, 2025
The increasing technical complexity of the renewable energy space has increased the demands on capital raising for those in the sector.
November 7, 2025
JA Solar has signed a module supply agreement with EPC contractor Larsen & Toubro (L&T) for two utility-scale projects in Uzbekistan. 
November 7, 2025
Saatvik Green Energy, through its subsidiary Saatvik Solar Industries, secured solar PV module orders worth INR2.99 billion (US$33.7 million). 
November 7, 2025
The US Geological Survey (USGS) has released the 2025 List of Critical Minerals, which includes silicon and tellurium.
November 7, 2025
Members of the European Parliament are urging the European Commission to restrict Chinese solar inverter manufacturers’ access to the bloc’s energy infrastructure, due to cybersecurity concerns.
November 7, 2025
Renewables asset fund Alantra Solar has secured €355 million to support the development and construction of five solar PV projects in Italy.

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
November 12, 2025
10am PST / 1pm EST
Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal