Rush to build UK solar projects ‘storing up grid problems’

Facebook
Twitter
LinkedIn
Reddit
Email

The rush to have projects connected ahead of a key deadline under the UK’s main large-scale solar support mechanism has the potential to cause future grid problems, the boss of a connection engineering firm has warned.

Speaking to PV Tech’s sister site, Solar Power Portal, Dragon Infrastructure Solutions chief executive Simon Phipps said “significant risks” were being taken by contractors in order to have projects finished to deadline and that too much extra-high voltage capacity was being installed in a short space of time.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The pressure we’re all under to deliver these infrastructures within a ridiculously short space of time at 33,000V is just lunacy.

“It’s really not the way to do business, but those are the ground rules that have been laid out by the government,” Phipps said.

Tomorrow, 31 March, is the deadline for developers to complete large-scale projects in order to qualify for the 1.4 renewable obligation certificate level. After that RO support will only be available for projects under 5MW and at a lower level of 1.3.

Last year developers faced major difficulties completing projects before the last ROC deadline after extended periods of poor weather and flooding hampered construction efforts and caused significant delays.

But while Phipps said this year’s weather had been “almost perfect”, delays in obtaining approval and the requisite licences from various authorities have caused similar delays, resulting in another pre-deadline construction rush.

Earlier this month business rescue specialist McTear Williams & Wood warned that one in 10 large-scale solar projects in the UK could be at risk of missing out on funding, a figure Phipps agreed “sounded about right”.

“There’s so much money involved in these contracts – there’s hundreds and hundreds of millions of pounds… [and] developers have gotten themselves into a position where they've spent too much money to back out, as they can't afford to lose that money so they've got to go for it,” Phipps said.

Read Next

May 14, 2026
Kiwa PVEL has rolled out updates to its module testing programme, with two changes affecting Static Mechanical Load (SML) and hail testing.
May 14, 2026
Arava Power has acquired 50% of OCI Energy’s La Salle Solar project, a 670MW project that OCI expects to start commercial operations in 2028.
May 14, 2026
Norway-headquartered technical and safety expert DNV has published two new standards for the design and maintenance of floating solar PV (FPV) systems.
May 14, 2026
New Zealand's government has ordered a sector review into the installation of residential and small to medium-scale solar, aiming to reduce what it describes as a "red tape nightmare" that can delay approvals for months.
May 13, 2026
US solar manufacturer T1 Energy has registered a record quarterly net income and adjusted EBITDA in the first quarter of 2026.
May 13, 2026
RWE has commissioned its 273.6MW Emily Solar project in Illinois, taking the developer’s operating renergy portfolio in the state to 1GW. 

Upcoming Events

Solar Media Events
May 20, 2026
Porto, Portugal
Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA