Rush to build UK solar projects ‘storing up grid problems’

Facebook
Twitter
LinkedIn
Reddit
Email

The rush to have projects connected ahead of a key deadline under the UK’s main large-scale solar support mechanism has the potential to cause future grid problems, the boss of a connection engineering firm has warned.

Speaking to PV Tech’s sister site, Solar Power Portal, Dragon Infrastructure Solutions chief executive Simon Phipps said “significant risks” were being taken by contractors in order to have projects finished to deadline and that too much extra-high voltage capacity was being installed in a short space of time.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The pressure we’re all under to deliver these infrastructures within a ridiculously short space of time at 33,000V is just lunacy.

“It’s really not the way to do business, but those are the ground rules that have been laid out by the government,” Phipps said.

Tomorrow, 31 March, is the deadline for developers to complete large-scale projects in order to qualify for the 1.4 renewable obligation certificate level. After that RO support will only be available for projects under 5MW and at a lower level of 1.3.

Last year developers faced major difficulties completing projects before the last ROC deadline after extended periods of poor weather and flooding hampered construction efforts and caused significant delays.

But while Phipps said this year’s weather had been “almost perfect”, delays in obtaining approval and the requisite licences from various authorities have caused similar delays, resulting in another pre-deadline construction rush.

Earlier this month business rescue specialist McTear Williams & Wood warned that one in 10 large-scale solar projects in the UK could be at risk of missing out on funding, a figure Phipps agreed “sounded about right”.

“There’s so much money involved in these contracts – there’s hundreds and hundreds of millions of pounds… [and] developers have gotten themselves into a position where they've spent too much money to back out, as they can't afford to lose that money so they've got to go for it,” Phipps said.

Read Next

November 26, 2026
Veteran Chinese PV manufacturer HT‑SAAE plans to offload its remaining 15% stake in its Turkish subsidiary, HT Solar Energy, established a decade ago.
November 25, 2026
A report from think tank Ember has highlighted six policy reforms in Indonesia that would accelerate the country’s 100GW solar PV target.
November 25, 2026
A combination of recent grid and zoning reforms in Poland have created “a bit of a deathtrap” for project developers.
November 25, 2026
Romania's new grid-capacity allocation process reveals the true cost and timing of developing a replacement project, strengthening the case for investors to pursue ready-to-build opportunities already on the market, writes Horia Grigorescu.
November 25, 2026
Spanish independent power producer Grenergy has signed a 15-year solar PV power purchase agreement in Peru with an investment-grade utility.
November 25, 2026
The Asian Development Bank has approved US$20 million of financing for Kyrgyzstan’s first utility-scale floating PV power plant.

Upcoming Events

Solar Media Events, Upcoming Webinars
December 9, 2026
10am GMT / 11 CET
Solar Media Events, Upcoming Webinars
December 16, 2026
9am PST
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 18, 2028
Istanbul, Türkiye