Rush to build UK solar projects ‘storing up grid problems’

Facebook
Twitter
LinkedIn
Reddit
Email

The rush to have projects connected ahead of a key deadline under the UK’s main large-scale solar support mechanism has the potential to cause future grid problems, the boss of a connection engineering firm has warned.

Speaking to PV Tech’s sister site, Solar Power Portal, Dragon Infrastructure Solutions chief executive Simon Phipps said “significant risks” were being taken by contractors in order to have projects finished to deadline and that too much extra-high voltage capacity was being installed in a short space of time.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The pressure we’re all under to deliver these infrastructures within a ridiculously short space of time at 33,000V is just lunacy.

“It’s really not the way to do business, but those are the ground rules that have been laid out by the government,” Phipps said.

Tomorrow, 31 March, is the deadline for developers to complete large-scale projects in order to qualify for the 1.4 renewable obligation certificate level. After that RO support will only be available for projects under 5MW and at a lower level of 1.3.

Last year developers faced major difficulties completing projects before the last ROC deadline after extended periods of poor weather and flooding hampered construction efforts and caused significant delays.

But while Phipps said this year’s weather had been “almost perfect”, delays in obtaining approval and the requisite licences from various authorities have caused similar delays, resulting in another pre-deadline construction rush.

Earlier this month business rescue specialist McTear Williams & Wood warned that one in 10 large-scale solar projects in the UK could be at risk of missing out on funding, a figure Phipps agreed “sounded about right”.

“There’s so much money involved in these contracts – there’s hundreds and hundreds of millions of pounds… [and] developers have gotten themselves into a position where they've spent too much money to back out, as they can't afford to lose that money so they've got to go for it,” Phipps said.

Read Next

June 1, 2026
Nextpower has filed a patent lawsuit against GameChange Energy on the same day GameChange announced a strategic consolidation of its activities and rebrand.
June 1, 2026
SEG Solar will build a third module manufacturing plant in the US that will bring the company’s total manufacturing capacity to 10.6GW.
June 1, 2026
Grenergy has signed a 12-year hybrid power purchase agreement (PPA) in Chile linked to the fifth phase of its Oasis de Atacama solar-plus-storage platform.
Premium
June 1, 2026
What financing options are there for renewable developers who find themselves shut out of some of Europe’s supportive auction programmes?
June 1, 2026
EDF power solutions North America has signed a 30-year PPA to sell power generated at the 400MW Utah Solar 1 Energy project to the LADWP.
June 1, 2026
Indian independent power producer (IPP) Sunsure Energy has commissioned a 105MWp solar plant in Uttar Pradesh's Mahoba district.

Upcoming Events

Media Partners, Solar Media Events
June 2, 2026
Johannesburg, South Africa
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA
Media Partners, Solar Media Events
June 30, 2026
Sacramento, California
Media Partners, Solar Media Events
August 25, 2026
São Paulo, Brazil