Southern Power starts commercial operations at second phase of Millers Branch solar farm, signs seven-party VPPA

Facebook
Twitter
LinkedIn
Reddit
Email
A Southern Power solar PV project.
Upon the completion of all three phases of the Millers Branch solar project, it will have a combined capacity exceeding 500MW. Image: Southern Power.

US electric company Southern Power has started commercial operations at the 180MW second phase of its Millers Branch Solar Facility in Haskell County, Texas.

The second phase is marginally smaller than the first phase of the project—which stands at 200MW—and was announced by Southern Power in 2024 following its acquisition of the Millers Branch project from EDF Renewables. The successful completion of construction work and start of commercial operations at the second phase is in line with Southern Power’s initial timeline for the project, and the phase is notable for the multi-party offtake deal that has been signed to acquire renewable energy credits generated by the project.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Southern Power has signed a series of virtual power purchase agreements (VPPAs) with seven buyers for the project’s output. These include Cisco (which will acquire certificates generated by a 50MW portion of the project); Juniper Networks (40MW), Bio-Rad Laboratories, Cadence and IDEXX Laboratories (20MW); and PTC (10MW). A further unnamed “large healthcare company” was also identified as offtaker for the remaining 20MW of capacity.

This multi-buyer approach was coordinated by the Sustainability Roundtable, a US-based platform that aims to facilitate such deals through its ‘Net Zero Consortium for Buyers’ (NZCB) structure. Southern Power has already signed an offtake agreement for the third phase of the Millers Branch project, with a capacity of 132MW, which also uses the NZCB structure, with Synopsys and Keysight signing VPPAs for the project’s output.

Sustainability Roundtable notes that its NZCB structure has facilitated deals for 1GW of renewable energy capacity and plans to add another gigawatt of capacity in the coming years.

The news follows a number of advancements in the massive Texas solar PV sector, including the completion of construction work at a phase of Origis Energy’s 2GW solar-plus-storage project in the state, and the signing of a plethora of more conventional PPAs. Among the offtakers are tech giants Tesla, Meta and Microsoft.

Read Next

Premium
November 13, 2026
As US voters backed data centre moratoriums in the midterms, this raises questions over solar PV's AI-linked growth in the years ahead.
November 13, 2026
Teraco has selected JA to deliver n-type solar PV modules to its 120MW Sediba solar PV project in Parys, Free State province, South Africa.
November 13, 2026
Rezolv Energy has announced its partners for the construction of Dama Solar, its 1.36GWp solar PV project in Arad County, western Romania.
November 12, 2026
Terra-Gen completes PV park in California, Duke Energy Florida plans four new solar arrays, and Altus Power acquires another 92 projects.
November 12, 2026
Investing in a portfolio that includes solar PV projects and BESS is a key tool to reduce exposure to price risk, according to Pexapark.
November 12, 2026
Almost 2GW of PV capacity is to be put out to tender in the latest phase of Saudi Arabia’s renewable energy procurement programme.

Upcoming Events

Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye