Total Eren and New Energy Solar have both hit milestones for major PV projects in Australia, with the former hitting financial close for a plant in the Victoria state.

The 256.5MW first phase of Total Eren’s Kiamal scheme will be backed with US$175 million in debt funding from Australian bank ANZ, as well as Dutch and French counterparts ING and Natixis.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The work of EPC Biosar, the project is being described as Victoria’s largest solar plant to date. Construction, set to add some 718,000 PV panels and single-axis trackers, should conclude later this year.

Kiamal’s first phase will also be backed by Australia’s state-owned green bank CEFC, which recently bought a US$35 million minority stake. It is backed by four PPAs – including with food giant Mars – and large-scale generation certificates with energy trader Origin Energy.

According to Total Eren, the 256.5MW frontrunner will be followed by a 213.5MW Kiamal second stage. Commercial options are being “explored” for a separate 270MW energy storage element, the firm explained.

All systems go for PV-powered Sydney trains

Across state lines, in Australia's New South Wales, a 110.9MW PV plant has initiated supply to state capital Sydney.

The installation, a project by New Energy Solar, is located a four-hour drive northwest of Sydney but will help power trains at the 4.7-million-inhabitant city under a 15-year PPA with Sydney Metro.

New Energy Solar acquired the Beryl project last year from First Solar Australia, which will continue to oversee O&M going forward.

The plant, New Energy Solar CEO John Martin said in a statement, reached commercial operations “on time and on budget” despite the 2.5MW capacity increase agreed this February.

Equipped with LONGi modules, Beryl was switched on as a separate New Energy Solar project – 199.6 MWDC Mount Signal 2 – remains under construction, with plans to hit commercial launch before the end of 2019.

Read Next

January 30, 2026
India Power Corporation Limited has partnered with Bhutan’s Green Energy Power Private Limited to develop a 70MWp solar power plant in Paro, Bhutan
January 30, 2026
 Scatec has reported strong fourth-quarter results with proportionate revenues increasing 25% year-on-year to NOK3,362 million (US$2.68 billion).
January 30, 2026
A 132MW solar PV project from French renewables company Voltalia has been selected by the Tunisian government for construction.
Premium
January 30, 2026
In an interview with PV Tech Premium, two UNSW researchers emphasise the need for enhanced UV testing for TOPCon solar cells.
January 29, 2026
The cost of Chinese solar module manufacturing will rise in the first half of 2026, though prices may fall again before the end of the year.
January 29, 2026
PV module defects are increasing as manufacturers struggle to achieve consistent quality through robust bill-of-material and process controls.

Upcoming Events

Solar Media Events
February 3, 2026
London, UK
Upcoming Webinars
February 18, 2026
9am PST / 5pm GMT
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA