Premier Energies moves ahead with 10GW ingot-wafer facility in Andhra Pradesh, India

Facebook
Twitter
LinkedIn
Reddit
Email
The Telangana facility can produce four G12R zero busbar tunnel oxide passivated contact (TOPCon) modules every 16 seconds, the company said. Image: Premier Energies.
Production is scheduled to begin in the first quarter of 2028, Vinay Rustagi, chief business officer at the company, told PV Tech. Image: Premier Energies.

Indian PV manufacturer Premier Energies expects to begin construction of the first phase of its planned 10GW ingot and wafer manufacturing facility in Andhra Pradesh shortly.

Production is scheduled to begin in the first quarter of 2028, Vinay Rustagi, chief business officer at the company, told PV Tech.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The confirmation follows reports by several Indian news outlets that Premier plans to invest around INR60 billion (US$628 million) over the next three years to establish ingot and wafer manufacturing capacity.

The investment forms part of Premier Energies’ broader INR125 billion capital expenditure programme, which includes expanding its solar cell and module manufacturing capacity as well as entering adjacent businesses including inverters, batteries and transformers.

The Andhra Pradesh government has approved the project and allocated 200 acres of land in Naidupeta, near Tirupati, where the company plans to establish 10GW of annual ingot production capacity and 10GW of wafer capacity. The investment is intended to position Premier Energies as a “fully integrated solar manufacturer” ahead of the Indian government’s requirement for domestic production of ingots and wafers from 2028.

Confirming the project timeline Rustagi said, “We expect to start construction of the first 5GW phase shortly and finish it by December 2027 to commence production in Q1 2028. The second phase of 5GW is proposed to be completed by end 2028. Our aim is to become a fully integrated manufacturer with 10GW plus capacity across ingots-wafers-cells-modules.”

The ingot and wafer investment forms part of a wider expansion that will increase Premier Energies’ manufacturing footprint, with the company planning to more than double its solar cell and module production capacities to 10.6GW and 11.1GW, respectively, while expanding into additional clean energy equipment manufacturing.

Premier Energies currently operates solar manufacturing facilities around Hyderabad in Telangana, producing 3.6GW of solar cells and 11.1GW of modules annually.

Asked whether the company is considering further expansion beyond Andhra Pradesh and Telangana, Rustagi confirmed that no decision has yet been made.

“While our existing plants are located around Hyderabad in Telangana, our new cell and ingot-wafer plants shall be based in Naidupeta, Andhra Pradesh. For our next phase of expansion, we are still examining options,” he said.

Premier Energies secures US$315 million solar module and cell orders

In other news, Premier Energies has secured orders worth INR30.11 billion (US$350 million) during the April-June quarter of fiscal year 2027, covering the supply of 1,846MW of solar cells and modules.

The orders, which will be delivered across FY2027 and FY2028, have been received from a mix of power producers, module manufacturers, engineering, procurement and construction (EPC) companies and other customers, according to the company.

Chiranjeev Saluja, managing director, Premier Energies, said, “Premier Energies is embarking on a high-growth strategy supported by booming solar demand and the Indian government’s policy commitment to Make-in-India. Timely implementation of ALMM-II policy, as recently announced, for domestic manufacturing of solar cells is a critical enabler of business growth. These new orders reflect the leadership position built by Premier Energies with investments in new technologies, scale and product quality.”

Premier Energies said the order inflow reflects customer confidence in its manufacturing capabilities, product quality and execution track record.

The new contracts come as the company expands its manufacturing footprint in India. Premier Energies recently increased its module manufacturing lines from 5.5GW to the current 11.1GW of annual nameplate production capacity, while its solar cell capacity is expected to rise from 3.6GW to 10.6GW by September 2026.

22 October 2026
India Expo Mart, Greater Noida
Whether you're looking for new technologies, trusted partners, or fresh business opportunities, you'll find them at the 19th Renewable Energy India Expo 2026. Join 55,000+ industry professionals and 1,000+ exhibiting brands across 14 halls featuring solar, bioenergy, battery storage, and the Germany Pavilion. It's where the clean energy sector comes together to exchange ideas, build partnerships, and drive business forward.

Read Next

October 19, 2026
ACME Solar has signed a 300MW/1,200MWh PPA with the Solar Energy Corporation of India (SECI) for a solar-plus-storage portfolio.
October 19, 2026
The skilled worker shortage was one of the key discussions from solar manufacturers at last week's PV CellTech USA Conference.
October 16, 2026
Eleven German associations oppose proposed solar prosumer grid fees, warning they could deter investment and slow expansion.
October 16, 2026
Concord New Energy (CNE) has closed US$400 million in financing for its US clean energy and digital infrastructure portfolio.
October 16, 2026
Acciona, GenusPlus and UGL Engineering have been selected to deliver Stage 1 of Clean Energy Link – East (CEL-East), a transmission project in Western Australia.
October 15, 2026
Australia's solar financial investment decisions (FIDs) have hit a record 3.5GW in 2026, with energy minister Chris Bowen saying renewable energy investment "has already broken the annual record".

Upcoming Events

Solar Media Events, Upcoming Webinars
October 21, 2026
2pm AEDT
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye