MEMC says some production delays experienced in wake of Hurricane Ike

In the wake of Hurricane Ike, MEMC Electronic Materials has experienced some production slowdowns largely caused by delays in raw materials deliveries from suppliers to the company's Pasadena, TX, polysilicon plant. As a result, the company has updated its financial outlook targets and lowered its third-quarter revenue targets from a previous guidance range of $560 million-$620 million to $520 million-$540 million.

"Our Pasadena facility did not experience any apparent major damage, and we were able to start up the plant systems in preparation for production to begin Monday, Sept. 14, as planned," said MEMC CEO  Nabeel Gareeb. "However, some of our regional suppliers had startup difficulties primarily due to power availability, plant issues, and pipeline damage as a result of the hurricane, preventing them from starting high-volume delivery of some raw materials until yesterday (Sept. 23)."

"This resulted in the Pasadena facility running at very low utilization levels through the early part of this week," he continued. "We now believe we are at the tail end of these raw material issues, which should allow us to achieve normal production rates within the next few days.

"Assuming there are no significant issues during this ramp, we now expect the cumulative impact of these delays to be approximately 15 days' worth of production instead of the 5 days originally forecasted. Consequently, we are now targeting third-quarter 2008 revenue to be approximately $530 million, plus or minus $10 million, with gross margin of approximately 51%, plus or minus 1%. Operating expenses are still targeted to be approximately $43 million.

"We do not expect any long-term impacts from these delays nor do we expect any significant interruption to our ongoing capacity expansion activities. We would like to publicly recognize the commitment and hard work of our employees, as well as those of our vendors, in enabling us to recover from the effects of this storm, in spite of the challenges the hurricane has presented to them in their personal lives," concluded Gareeb.

-- Tom Cheyney

Newsletter

Preview Latest Subscribe
We won't share your details - promise!

Publications

  • Photovoltaics International 16th Edition

    Photovoltaics International 16th Edition

    This sixteenth edition of Photovoltaics International marks four years of production of the quarterly journal. As always, our focus is on efficiency and quality improvement and cost reduction in manufacturing. As 2012 rolls along, companies are falling by the wayside due to supply and demand issues, ASP declines and drastic governmental subsidy cuts. A clear picture of 2012 is offered through papers from the likes of TÜV Rheinland, Fraunhofer ISE, SEMI PV Group and EPIA, amongst others.

  • Photovoltaics International Lite, Volume 05 - 2011

    Photovoltaics International Lite, Volume 05 - 2011

    This digital interactive Lite sees Tom Cheyney follow Agua Caliente’s progress on becoming one of first truly utility-scale PV power farms, where 40–50MW (AC) will be commissioned by the end of the year. We also feature one of the world’s largest silicon thin-film PV power plants, Avenal; a report on warnings of the collapse of module prices from Solarbuzz and PI-Berlin presents tips on PV module testing. A print version of this edition will be distributed at Solar Power International 2011 in Dallas, Texas.

  • Manufacturing The Solar Future: The 2012 Production Annual

    Manufacturing The Solar Future: The 2012 Production Annual

    Manufacturing the Solar Future 2012, the second in the Photovoltaics International PV Production Annual series, delivers the next installment of in-depth technical manufacturing information on PV production processes.

Partners

Acknowledgements

Solar Media