China 17.8GW, a record solar PV installation target for 2015. Achievable?

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on reddit
Reddit
Share on email
Email

On 16 March, just a few days after the 10-day annual National People’s Congress concluded in Beijing, China’s top energy regulator, the National Energy Administration (NEA), released the official solar PV installation target for 2015 of 17.8GW, thus replacing a 15GW target communicated via a draft circular earlier in late January. The 17.8GW is not only 20% higher than the tentative target of 15GW, but also 27% higher than the 2014 target of 14GW.

This rather aggressive target of 17.8GW demonstrates the regulator’s determination to deploy solar power across the country. Its aggressiveness appear not to derive from the expectation that the 35GW target set in the current 12th Five-Year-Plan for Solar Development (2011-2015) will be missed in its final year, because according to NEA’s statistics, by the end of 2014 China’s total installed PV power generation capacity amounted to 28.05GW, so just 7GW shy of what as a minimum is expected under the plan. Assuming the 17.8GW will indeed be realised, by the end of 2015 China would then be home to 45GW of installed PV capacity thereby not only exceeding its 35GW target by a good 30%, but as well overtaking Germany’s pole position in terms of installed capacity, which at the end of 2014 amounted to approximately 37.6GW, thus becoming the country with the world’s largest installed solar PV power generation capacity.

Utility versus distributed

One surprise about the 17.8GW is that it no longer stipulates any specific target for either utility-scale (ground-mounted) or distributed generation (ground-mounted up to 20MW in certain areas and rooftop). This deviates from the government’s former policy line of explicitly promoting distributed generation, even though this has been on top of the political agenda since August 2013. Growing grid curtailments in particular in provinces across China’s West due to a relatively undeveloped grid infrastructure, low local power consumption or long-distance transmission lines under construction urged the government to favour distributed generation under its motto “on-site generation and on-site consumption”, focusing on industrial and commercial rooftop applications. Against this backdrop a total of 1,823MW of distributed demonstration projects were approved and scheduled to be realised in 18 designed industrial and development zones by the end of 2015. However, despite these efforts, achievements fell short of set targets: in 2013 out of 10.95GW installed (according to revised NEA figures) just 800MW were considered ‘distributed generation’ and last year out of the 8GW target for distributed generation just 2.05GW (including both rooftop and specific ground-mounted systems up to 20MW) were realised.

The author argues, given the local circumstances hampering the smooth execution of solar rooftop projects across China, in particular identification of rooftop ownership, identification of structurally sufficient roofs, average lifetime of buildings below 20 years and insufficient financing, among other reasons, the government should move away from its former ‘hard’ target policy towards a ‘soft’ target policy. Not setting specific targets for various types of applications would allow the local governments and companies to develop projects not subject to a myriad of constraints. Such flexibility would possibly ensure a greater success in terms of installations given that according to official statistics last year just 10.60GW of the targeted 14GW were achieved.

The official 2015 target notification does however encourage local governments when elaborating their respective local construction plans to prioritise projects up to 20MW in 35kV areas and (66kV areas in north-east provinces), thus implying that distributed projects are still being favoured. Such local development plans shall be submitted to NEA by late April for official approval. In this context, once projects have been approved, a monthly monitoring and supervision scheme will come into effect, helping in particular the central government to reassess the overall progress. Depending on actual progress central government will then determine which provinces will be rewarded with an increase or face a potential decrease of their quota for next year.

The new target also includes 1.5GW of poverty alleviation pilot projects spread across in total six provinces. Counties targeted for pilots are those where at least 200 households have a disposable income of less than RMB3,000 (US$484) a year, with such households qualifying for a 3kW solar system.  system The required budget for the hardware procurement will be provided by the provincial and central government. The author assumes that the inclusion of 1.5GW for poverty alleviation is to be seen in the context of the central government’s efforts to achieve a 100% nationwide electrification by the end of 2015.

Along with the 2015 target announcement, the NEA is “re-introducing” competitive mechanisms in an attempt to reduce the fixed solar feed-in tariff. For example, local governments are encouraged to allocate construction quotas or project developing rights to companies with sound financial health and adhering to technology guidelines, such as deployed modules having to achieve minimum efficiency levels set earlier by the Ministry of Industry and Information Technology (MIIT). The proposed “encouragement” implies some form of bidding process, similar to projects which NEA put up for tender and invited the industry to bid for in 2009/2010.

Overall, the 17.8GW target, even without taking into account 1.5GW for poverty alleviation, is undeniably ambitious. If successful, annual installations would increase by almost 70% year on year. Replacing the apparently impractical hard target policy with a more flexible and pragmatic approach, taking into account the local conditions and allowing utility-scale projects if needed, makes the target easier to achieve. Constraints associated with distributed generation projects as briefly elaborated above won’t disappear in the near future, hence the new approach ensures that the gap can be filled with utility projects.

However, the re-introduction of a competitive mechanism as a means to reduce the FiT is perceived by the author as a critical approach, in so far as developers will be pressured to offer a lower FiT in order to obtain official project approval, thus reducing the financial attractiveness of such projects. Also, through the offering of lower FiTs is there perhaps the possibility that overall system quality will be compromised and therefore long-term sustainability jeopardized?

A relatively tight timeline and near-term milestones, quotas for certain provinces which lack attractiveness, some sort of unproven bidding process, financial support lacking, prevailing grid curtailment constraints in certain regions, among other reasons makes it at this stage challenging to determine whether the 17.8GW target is indeed achievable. AECEA is of the opinion that by mid May, once the provincial constructions plans shall have received official approval by NEA overall visibility until the end of 2015 shall have improved.

China has set itself a 17.8GW PV target for 2015. United PV.
11 May 2021
Join this Talesun Solar webinar focused on providing an insight into the company’s next-generation series of large-area, high-efficiency PERC (Passivated Emitter Rear Cell) modules. These are available in both monofacial (‘BiStar’) and bifacial (‘BiPro’) formats, using 182mm half-cut cells in 144 and 156 cell configurations and provide up to 590Wp performance with efficiencies of up to 21.2%.
11 May 2021
Green Hydrogen: always the future never the now? Join us on 11-12 & 18-19 May for a fresh look at what’s fast becoming a reality. Governments across the world have put hydrogen at the centre of their decarbonisation plans with billions of dollars allocated to stimulating the market and whilst individual strategies will differ, the theme is the same: green hydrogen is the fuel of the future. Its role goes beyond energy use and there is already an active off-take market. From the perspective of renewable generators, hydrogen can play a pivotal role in enabling unsubsidised projects to work in a low power price environment and provide another business model in areas where the grid is congested. Hydrogen could also be the driver of a new wave of renewable installations as countries’ hydrogen plans hinge on new capacity being available.
26 May 2021
Tara Doyle and Tristan Erion-Lorico of PV Evolution Labs (PVEL), will share this year’s top-performing modules and discuss key findings from PVEL’s PQP testing. Join us to explore which find out which new Top Performer category can affect project value by more than $100,000 – and which test resulted in >20% degradation.
15 June 2021
Looking at the drivers and dynamics of utility scale solar in the UK over the next five years. This event will consider the immediate challenges as we enter the build phase in the UK market where we could see as much as 3GW deployed in 2021 alone! What developments will continue the growth of 100MW+ sites and what impact will government policy have on the rate of deployment in the UK? Join leading developers and manufacturers shaping the direction of one of Europe’s most active markets and hear from speakers with a history of influencing innovation and change.
6 July 2021
Explore in depth the opportunities of the different countries via case studies, business and financial models that will foster growth in the region with particular focus on Thailand, Philippines, Indonesia, Taiwan, Korea, Cambodia, Singapore, Malaysia & Vietnam.
13 July 2021
Energy Next is a new industry exhibition focusing on the latest renewable energy and energy efficiency technology, which will be held for the first time in 2021 in Sydney, Australia alongside the Clean Energy Council’s Australian Clean Energy Summit, the peak gathering of leaders driving Australia's energy transformation. Organised by the same people behind Australia’s largest clean energy event, All-Energy Australia, Energy Next will give visitors two days of access to key suppliers in the industry, free-to-attend professional development and industry workshops, and networking opportunities to better understand clean energy issues and solutions and learn about the latest developments in this transformational, dynamic sector.

Read Next

May 5, 2021
Europe’s solar industry has lauded the inclusion of a commitment to "re-ignite" Europe's solar manufacturing sector within the European Commission’s refreshed industrial strategy.
May 5, 2021
A round-up of news from the US solar sector, including updates from the Department of Energy, private equity firm American Securities, and Indiana developer Hoosier.
May 5, 2021
New solar and wind assets in the US are now cheaper to operate than nearly 80% of existing coal-fired generators in the country and could replace the asset class while delivering numerous benefits to consumers, a report has found.
May 5, 2021
Governments worldwide must ensure that there are sufficient raw materials available to solar and energy storage developers to safeguard the energy transition.
May 5, 2021
The Australian Renewable Energy Agency (ARENA) has selected three commercial-scale green hydrogen projects that will share in AU$103 million (US$79.7 million) of funding to support their development.
May 5, 2021
SHV Energy, a Netherlands-based liquified petroleum gas (LPG) distributor, has acquired a majority stake in Indian solar developer SunSource Energy.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
May 11, 2021
Upcoming Webinars
May 26, 2021
Session 1 - 7:00 AM (BST) | Session 2 - 5:00 PM (BST)
Solar Media Events
June 15, 2021
Solar Media Events
July 6, 2021