‘Decisive action on climate’: World’s largest solar PV and battery project underway in Philippines

November 25, 2024
Facebook
Twitter
LinkedIn
Reddit
Email
Philippines president Ferdinand Marcos Jr speaks at the event. Image: Presidential Communications Office

Philippines president Ferdinand Marcos Jr attended as construction began on what is thought to be the world’s largest power plant to combine solar PV and battery storage.

The Southeast Asian country’s presidential communications office announced last week (21 November) that Marcos Jr. attended the groundbreaking celebration for the Meralco Terra Solar project in Gapan City, about 100 km from the capital Manila.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project will include 3.5GWp of solar PV generation capacity and a 4.5GWh battery energy storage system (BESS), which will be built across 3,500 hectares of land in the two provinces of Bulacan and Nueva Ecija.

The government has prioritised its speedy development. In August, the national Board of Investments (BOI) fast-tracked Meralco Terra Solar with the issue of a so-called ‘green lane certificate’.

This would expedite the permitting and licensing process for the plant, as reported by Energy-Storage.news. The BOI is an agency of the government Department of Trade and Industry with a remit to stimulate investment into different kinds of projects that align with national policy objectives.

Although at that time, the total cost of the project was estimated to be PHP185 billion (US$3.14 billion), the presidential communications office statement yesterday quoted a figure of PHP200 billion.

In a speech, the president said that the project represents “decisive action towards helping address global warming and climate change.” The Philippines’ main island of Luzon, where Manila and Gapan are both located, has just been struck twice by super typhoon Pepito. According to BBC reporting, it is the sixth typhoon to hit the country within a month.

A claim that the project is the largest in the world appears to hold up.

The world’s biggest solar PV plant is the 5GW Xinjiang Solar project in the northwest of China’s Xinjiang region, which went online earlier this year through state-owned Ürümqi Zhonglvdian New Energy Co Ltd, but does not include battery storage.

Meanwhile, developer Terra-Gen’s Edwards & Sanborn solar-plus-storage project in California, US, is thought to feature the world’s biggest lithium-ion (Li-ion) BESS facility to date at 3,287MWh, alongside 875MWdc of solar PV.

Edwards & Sanborn, built and commissioned in phases, went fully into commercial operation at the beginning of this year.

That said, over in Latin America, a project pairing 2GW of solar PV and up to 11GWh of battery storage is currently being built in seven phases in Chile. Spanish IPP Grenergy is developing the Oasis de Atacama project, and its first four phases are due to be in operation by the end of 2026, with Chinese BESS suppliers BYD and CATL contracted to work on them.

Meanwhile, Meralco Terra Solar is scheduled to go into commercial operation by 2027, Marcos Jr said. It will connect to the grid via an existing 550kV transmission line and later linked to a new-build transmission line in the region.

Last week, Terra Solar Philippines awarded the project’s engineering, procurement and construction (EPC) contract to China Energy Engineering Group (Energy China).

To read the full version of this story, visit Energy-Storage.news.

Read Next

April 28, 2026
Data centres have emerged as the primary driver of electricity demand growth for utility Origin Energy in Australia.
April 24, 2026
The European Commission (EC) has launched a new strategy to address the fossil fuel energy crisis in the Middle East and accelerate the “shift to homegrown, clean energies”, said EC president Ursula von der Leyen.
April 23, 2026
Renalfa IPP has secured funding from the European Bank for Reconstruction and Development (EBRD) for its Szihalom 450MW solar-plus-storage project in Hungary.
April 23, 2026
New York state has granted final siting permits to the AES Corporation’s 125MW Sugar Maple solar-plus-storage project.
April 22, 2026
Independent power producer Lydian Energy has acquired a 1.5GW solar PV and battery energy storage system (BESS) portfolio in North America.
April 22, 2026
Work has begun on the 500MW Maun solar-plus-storage project in Botswana, which will be a cornerstone of the country's plan to reach 1.5GW of operational renewable energy capacity by the end of the decade.

Upcoming Events

Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain