Eskom: Yes Zuma, we will sign remaining PPAs….if they’re cheap enough

Facebook
Twitter
LinkedIn
Reddit
Email
Grid strain, overcapacity and now finance are among the reasons Eskom is listing for its delay in signing the outstanding renewable energy PPAs under the REIPPPP. Source: Flickr/Gavin Fordham

Eskom is conditionally committing to follow through with South African president Jacob Zuma’s announcement that the utility will indeed sign the remaining PPAs under the government’s renewable procurement programme (REIPPPP).

The president reaffirmed South Africa’s commitment to renewable energy in his State of the Nation Address on Thursday, and also emphasised that the government remains committed to signing PPAs – including the outstanding ones under the programme.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

This was news for the country, given that Eskom had left 37 IPPs in limbo after it refused to sign PPAs won in the latest round of the programme, citing overcapacity and the cost of energy as its reasons for stalling.

The renewable energy industry said that this refusal to sign was delaying investments totalling R57 billion (US$4.28 billion). The South African Renewable Energy Council had threatened litigation over the delay.

However, Eskom is reaffirming Zuma’s statement – on a conditional basis.

“We are not against renewable energy projects,” Eskom spokesman Khulu Phasiwe told PV Tech. “We have signed 64 of them and will continue to sign. However, the ones that are outside of our ability to pay for, those ones we will continue to try to negotiate.”

The concern for the cost of bringing renewable energy into the grid comes as Eskom’s interim CEO Matshela Koka valued the cost of renewable energy in the country at an investment of R9 billion.

Despite Zuma appearing to be rallying the utility into action with an explicit statement that the unsigned PPAs will go ahead, Eskom reiterated reasons why this may not go to plan immediately, with some negotiation still in the works.

However, according to Phasiwe, cost of the PPAs may not be too big a barrier for the utility to surmount:

“The price of projects in round 4.5 are generally reasonable, so yeah, we will sign them. In fact, the projects we signed during round 1 and 2 thereabouts, those were very expensive. When we first started this project, some of the projects were costing up to R3/kWh. The new ones are actually less than that, so there shouldn’t be any worry now.” 

25 November 2025
Warsaw, Poland
Large Scale Solar Central and Eastern Europe continues to be the place to leverage a network that has been made over more than 10 years, to build critical partnerships to develop solar projects throughout the region.

Read Next

August 8, 2025
This week several solar developers have raised funds for projects around the world, including BRUC in Europe, Greenalia in the US, Qair in Mauritius and CREC in Philippines.
August 8, 2025
German solar inverter manufacturer SMA Solar posted losses in the first half of 2025, as demand in the residential and corporate & industrial (C&I) solar sectors 'remains weak'.
August 8, 2025
US solar tracker manufacturer Array Technologies has posted revenue of US$362.2 million in the second quarter of this year.
Premium
August 6, 2025
PV Talk: LevelTen’s Andrés Acosta discusses how an oversupply of clean projects is shaping Europe’s PPA market.
August 6, 2025
Independent power producer (IPP) Scatec has secured BRL150 million (US$27 million) for its 142MW solar PV plant in Minas Gerais, Brazil. 
August 5, 2025
China’s leading polysilicon firms are reportedly considering shutting down one third of the country’s polysilicon capacity and restructuring the sector, following years of overcapacity and tumbling prices.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines