Eskom: Yes Zuma, we will sign remaining PPAs….if they’re cheap enough

Facebook
Twitter
LinkedIn
Reddit
Email
Grid strain, overcapacity and now finance are among the reasons Eskom is listing for its delay in signing the outstanding renewable energy PPAs under the REIPPPP. Source: Flickr/Gavin Fordham

Eskom is conditionally committing to follow through with South African president Jacob Zuma’s announcement that the utility will indeed sign the remaining PPAs under the government’s renewable procurement programme (REIPPPP).

The president reaffirmed South Africa’s commitment to renewable energy in his State of the Nation Address on Thursday, and also emphasised that the government remains committed to signing PPAs – including the outstanding ones under the programme.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

This was news for the country, given that Eskom had left 37 IPPs in limbo after it refused to sign PPAs won in the latest round of the programme, citing overcapacity and the cost of energy as its reasons for stalling.

The renewable energy industry said that this refusal to sign was delaying investments totalling R57 billion (US$4.28 billion). The South African Renewable Energy Council had threatened litigation over the delay.

However, Eskom is reaffirming Zuma’s statement – on a conditional basis.

“We are not against renewable energy projects,” Eskom spokesman Khulu Phasiwe told PV Tech. “We have signed 64 of them and will continue to sign. However, the ones that are outside of our ability to pay for, those ones we will continue to try to negotiate.”

The concern for the cost of bringing renewable energy into the grid comes as Eskom’s interim CEO Matshela Koka valued the cost of renewable energy in the country at an investment of R9 billion.

Despite Zuma appearing to be rallying the utility into action with an explicit statement that the unsigned PPAs will go ahead, Eskom reiterated reasons why this may not go to plan immediately, with some negotiation still in the works.

However, according to Phasiwe, cost of the PPAs may not be too big a barrier for the utility to surmount:

“The price of projects in round 4.5 are generally reasonable, so yeah, we will sign them. In fact, the projects we signed during round 1 and 2 thereabouts, those were very expensive. When we first started this project, some of the projects were costing up to R3/kWh. The new ones are actually less than that, so there shouldn’t be any worry now.” 

Read Next

July 31, 2026
Avaada has secured approximately US$1.3 billion in debt to fund a 2.15GW portfolio of hybrid and solar projects in Gujarat and Maharashtra.
July 31, 2026
First Solar reported net sales of US$1.06 billion for Q2 2026, down 4% year-on-year, while reaffirming its full-year 2026 guidance.
July 30, 2026
Walden has secured US$250 million from Crayhill Capital Management to support its 5GW US utility-scale solar PV and BESS pipeline.
July 30, 2026
Australia's CEC calls for a national ‘Renewable Resources Payment’ scheme, requiring a legislated payment for every MWh of renewables.
July 28, 2026
Vena Energy has reached financial close on its 500MW Ixus Bugallon solar PV project in the Pangasinan municipality of the Philippines.
July 28, 2026
Nadara has secured €1.2 billion (US$1.36 billion) to refinance a 1.5GW operational renewable energy portfolio, including 13 solar projects.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye