Interconnection queues and permitting issues among obstacles to US transmission upgrades

November 28, 2023
Facebook
Twitter
LinkedIn
Reddit
Email
The US market will be able to replace fossil generation with renewables with a strong transmission system. Image: National Grid

Long and unpredictable interconnection queues, permitting, the shortages of skilled labour and essential equipment and grid upgrade financing are the major obstacles to US transmission upgrades, according to US law firm Troutman Pepper.

The report – Unlocking U.S. Transmission Upgrades – Are We on The Cusp of Real Progress? – stated that over 2TW of electricity generation and storage developments were waiting in queues for grid interconnection in April 2023, of which solar, storage, and wind projects make up 95% of capacity.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Long queues and permitting issues

Currently, the queue is six times longer than it was in 2014, and there is now 60% more capacity waiting in interconnection queues than the total US power generating capacity of 1.25TW. The passage of the Inflation Reduction Act (IRA) lengthened the process, but the queue will be even longer in the years ahead.

Part of the reason for this phenomenon was that developers submitted more speculative generation projects into the queues, even if there was little chance these projects would be built. As a result, the organisations planning transmission assumed that all of these projects would be built, although some projects were unrealistic.

Adam Stern, director of utility-scale policy and business development at New Leaf Energy, said: “For transmission planners to be able to trust that the projects in the queue are going to be real, we need to bring a degree of certainty to the interconnection process. One way to bring certainty and help speed things up is to build more transmission and more places to connect to.”

The Federal Energy Regulatory Commission’s (FERC) recent Order No. 2023 endorsed the “first come, first serve” concept in transmission, prioritising generation projects that are commercially viable and showing little tolerance for developers clogging the queue with speculative projects.

Permitting was another major obstacle as new transmission projects require extensive engagement with landowners, including private individuals, companies, tribal groups, and public agencies such as the Bureau of Land Management and US Forest Service, which can delay transmission upgrades.

Landowners were also reluctant to accept new projects on or near their land, which could cause further delays.

David Getts, general manager of transmission developer SouthWestern Power Group, explained: “The fundamentals are the same everywhere, which is nobody wants a big ugly transmission line going near their backyard.”

Transmission projects crossing state borders could increase the number of bodies that need to be involved.

However, Ameren Transmission Company of Illinois chairman and president Shawn Schukar believes that permitting would be quicker if transmission providers were able to develop transmission lines along existing rights of way.

He said: “The opportunity is around re-using or re-looking at existing infrastructure right away, which land has already been impacted by development. While it isn’t perfect, it would help move things along.”

In July, the White House’s Council on Environmental Quality (CEQ) proposed a rule that would streamline and accelerate the permitting process for new renewable power facilities. The proposed rule would enforce changes to the National Environmental Policy Act (NEPA), a broad piece of legislation that oversees permitting for projects on federal land and was signed into law in the 1970s.

Worker and equipment shortages and paying for upgrades

The report stated that transmission planners’ workloads were higher than ever before across the US. Rick Vail, vice president of transmission at PacifiCorp, said there was a shortage of the actual technical planners that could perform all the study work, which was getting more complicated as more different types of power generation were being added to the grid.

Moreover, planning transmission upgrades was further complicated by the difficulty of securing the physical transmission infrastructure, including conductors and substations.

Schukar said: “I can tell you that we have materials today that, a year ago, the time from order to delivery was about nine months. Today, it’s three to four years because, even though we told them three years ago that this growth was coming, they didn’t expand because everybody wants to see the dollars upfront.”

Currently, transmission is a bigger part of that overall cost as more transmission is being built; this could raise customers’ energy bills in the short term.

Bill Marsan, executive vice president and general counsel at American Transmission Company (ATC), said: “The transmission build-out has to make sense on a customer’s bill in relation to what we’re charging them for the generation and what we’re charging for the distribution; and there’s got to be a rational allocation of cost to the consumer and probably not too much of a ramp-up in cost to customers.”

As upgraded transmission can bring multiple benefits to customers, such as decreased production costs, better system reliability, and resilience, Marsan added that the US market will never be able to effectively replace fossil generation with renewables without a strong transmission system.

Read Next

November 14, 2025
Developer rPlus Energies has acquired two solar and storage projects with the total capacity of 900MW in Ada County, Idaho.
November 14, 2025
International solar manufacturer Canadian Solar has posted stable financials in Q3 2025, as its solar module and battery energy storage system (BESS) sales shift.
November 13, 2025
Xcel Energy will have to provide higher-quality data, and introduce flexible tariffs, following a vote from the Colorado PUC.
November 13, 2025
US solar hardware manufacturer Create Energy and Swiss cable producer Stäubli have announced a partnership to produce a new solar connector product.
Premium
November 13, 2025
Analysis: The opening of Corning's Michigan wafer plant puts it in a strong position to supply US-made, FEOC-compliant products, while competition from outside remains scarce.
November 13, 2025
US tracker manufacturer FTC Solar has entered into a purchase agreement to acquire the remaining 55% stake in steel manufacturer Alpha Steel.

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal
Solar Media Events
June 16, 2026
Napa, USA