EGing to invest over US$144 million in major manufacturing upgrades and relocation

January 23, 2020
Facebook
Twitter
LinkedIn
Reddit
Email
The company also announced plans to undertake a major revamp and upgrade of its existing solar cell and module assembly operations in Changzhou to support its efforts to return to a competitive position in the industry. Image: EGing

China-based integrated PV manufacturer, EGing Photovoltaic is planning major manufacturing upgrades and production relocation to return to competitiveness after guiding a full-year 2019 net profit loss. 

EGing stated it would invest approximately RMB 1.0 billion (US$144 million) in a new 3GW ingot and wafering plant in in Hohhot, Inner Mongolia after acquiring a small local firm, Inner Mongolia Huayao Optoelectronics in 2019.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

EGing’s existing ingot and wafering operations have been based in Changzhou, China but were said face multiple economic pressures, due to high electricity costs and outdated production equipment.

The company noted that it become increasingly difficult to continuingly reduce production costs and increase efficiencies to offset continued price declines as rapid technical changes continued in upstream manufacturing.

The new ingot and wafering plant would take two to three years to build and start operation, according to the company.

The company also announced plans to undertake a major revamp and upgrade of its existing solar cell and module assembly operations in Changzhou to support its efforts to return to a competitive position in the industry. 

EGing stated it would introduce the industry's most advanced equipment and production lines at its Changzhou production base while taking an impairment charge of approximately RMB 220 million (US$31.7 million) on fixed assets.

The company plans new monocrystalline solar cell capacity of 1.5GW and 2.5GW of module assembly capacity. EGing did not provide capital expenditure or timelines for the major production revamp, yet this would include disposing of manufacturing equipment that had high energy and high material consumption.

Attention would also be focused on increasing R&D activities. According to PV Tech’s annual R&D spending report, Eging spent only around US$2.7 million on R&D in 2018, compared to a peak of US$21.3 million in 2015.

According to PV Tech’s annual R&D spending report, Eging spent only around US$2.7 million on R&D in 2018, compared to a peak of US$21.3 million in 2015.

EGing reported that it expected to make a net loss of around RMB 210 million to RMB 270 million for the full-year 2019, primarily due to the impairment charges. Eging had reported a net profit of RMB 68.6 million in 2018. 

The company said that product sales had increased by over 30% in 2019, compared to the previous year.

Read Next

November 14, 2025
Lightsource bp has started construction on its 330MWp Valle 3 and 4 project in Wamba, Valladolid, in the Castilla y Leon region of Spain. 
November 14, 2025
Developer rPlus Energies has acquired two solar and storage projects with the total capacity of 900MW in Ada County, Idaho.
November 14, 2025
International solar manufacturer Canadian Solar has posted stable financials in Q3 2025, as its solar module and battery energy storage system (BESS) sales shift.
November 13, 2025
Building a solar manufacturing supply chain has become a "strategic imperative" for Australia, Stellar PV CEO Louise Hurll told PV Tech.
Premium
November 13, 2025
PV Talk: Stellar PV has been awarded government funding for its plan to open a solar ingot and wafer plant in Australia. The company’s CEO Louise Hurll tells Shreeyashi Ojha why the time is right for Australia to develop its upstream manufacturing capacity.
Premium
November 12, 2025
PV Talk: Stefano N. Granata of STS discusses the growing momentum behind back contact cell technology as manufacturers and investors embrace higher-efficiency solutions.

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal
Solar Media Events
June 16, 2026
Napa, USA