Grid bottlenecks push Netherlands to renewable subsidy restrictions

July 3, 2019
Facebook
Twitter
LinkedIn
Reddit
Email
Over 5,170 of all 5,376 renewable schemes applying for SDE+ funding in the autumn 2019 round were PV projects (Credit: Flickr / Willem)

Dutch PV projects opting for subsidies this autumn will need to secure a preliminary green-light from network operators under new government plans, meant to alleviate grid congestion.

Renewable applicants for the Netherlands’ SDE+ feed-in premium programme will have to formally request connection points and produce documents showing capacity exists for their projects, Economy and Climate minister Eric Wiebes announced last Friday.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In a letter to Dutch MPs, the top official linked the policy changes to the need to shore up the Netherlands’ strained power grid, with the bottlenecks currently afflicting the Drenthe and Groningen provinces predicted now to expand elsewhere.

The minister’s missive singled out solar PV as a congestion driver. The industry’s shorter construction timeframes have seen grid operators struggle to anticipate – and invest to adjust to – the pace of installations where onshore wind was easier to absorb, Wiebes said.

Making an indicative all-clear from grid operators an SDE+ requirement will, the minister argued, ensure “only more promising projects” will apply. “This will prevent unnecessary subsidies being retained by projects that will ultimately not be realised,” he added.

PV body Holland Solar said it shared the government’s unease about bottlenecks but added it has “serious concerns” with the minister’s letter. “[The changes] threaten to block the market,” the association said on Twitter. “We do not think this is the intention.”

Dutch PV under political spotlight

The decision adds hurdles between solar and a subsidy programme decisive to its fate in the Netherlands. As PV Tech learned this year, deploying without SDE+ support can be tough in a country of lower sun yields, expensive land and relatively modest power prices.

Over 5,170 of all 5,376 renewable schemes applying for the SDE+ autumn 2019 funding round are PV projects, which requested €2.9 billion of the €4.8 billion applied-for total.

According to industry players, the backlog of existing SDE-backed schemes is significant, an issue the government is now keen to act against. Its estimates suggest up to 8.5GW of projects was subsidised between 2016 and 2018 alone.

Minister Wiebes described delays with this existing pipeline. Under current law, solar projects have 18 months (plants smaller than 1MW), three (rooftop plants of over 1MW) and four years (ground-mounted and floating plants) after their SDE+ decision to complete construction.

Rooftop PV applications have been, the minister letter said, “relatively poorly prepared”. “Of all techniques, the degree of realisation for [rooftop] projects is the lowest (60% on average) and the dropout fluctuates around 40%,” the document noted.

The government’s SDE+ changes pile more pressure on Dutch PV solar, already under policymaker scrutiny. Earlier this year, MPs considered freezing new authorisations for certain ground-mounted projects, with the ban eventually removed from the parliamentary motion.

See here to read the ministerial letter in full

3 November 2026
Málaga, Spain
Understanding PV module supply to the European market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of module supplier selection; product availability, technology offerings, traceability of supply-chain, factory auditing, module testing and reliability, and company bankability.

Read Next

January 16, 2026
Indian solar PV manufacturer Vikram Solar is transitioning its module portfolio to the G12R format, led by the HYPERSOL G12R series. 
January 16, 2026
Global tech giant Amazon has been approved as the buyer of the 1.2GW Sunstone solar project in Oregon, one of the largest solar PV projects in the US.
January 16, 2026
US C&I solar developer Altus Power has acquired four solar projects with a total capacity of 105MW from IPP Cordelio Power. 
January 16, 2026
Canada-based solar mounting systems provider Polar Racking has entered the Australian market through its involvement in the 240MW Maryvale solar-plus-storage project in New South Wales, marking the company's first project deployment in the country.
Premium
January 15, 2026
Analysis: Expected changes to the EU’s cybersecurity laws that could have significant implications for the continent’s solar industry have been delayed, reportedly due to disagreement between officials and member states over how far they should go.
January 15, 2026
Enphase has begun US shipments of its new IQ9N-3P three-phase gallium nitride-based microinverter aimed at commercial rooftops.

Upcoming Events

Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
November 3, 2026
Málaga, Spain