Totalenergies launches legal action against Trina Solar alleging breach of contract, fraud over US$300m order

Facebook
Twitter
LinkedIn
Reddit
Email
Trina Solar’s exhibition stand at the 2021 SNEC show in China. Image: PV Tech.

Totalenergies has launched legal action against major solar manufacturer Trina Solar, alleging fraud and breach of contract relating to a 900MW+ module order.

Court filings filed last week and seen by PV Tech show Totalenergies Renewables and US-based subsidiaries have launched the action in Alameda County, California, claiming that Trina breached contracts and acted fraudulently in relation to module orders worth around US$300 million, signed last year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Subsidiaries of Total entered into four implementation agreements for modules bound for four projects in the US – three in California, one in Texas – with the total order exceeding 900MW.

Those agreements included;

  • A US$115 million order for ~360MW of modules bound for the Danish Fields project in Texas, negotiated at a cost of US$0.32c/W DDP.
  • A US$22.8 million order for 71.2MW of modules headed for the Skysol project in California, negotiated at a cost of US$0.32c/W DDP.
  • A US$318 million order for 99.5MW of modules headed for the Ellis project in California, negotiated at a cost of US$0.32c/W DDP, and;
  • A contract valued at between US$115 – 121 million for ~380MW of modules for the Myrtle project in California, negotiated at a price of between US$0.305 – 0.32c/W DDP, the end price of which depended on the shipping solution chosen by Total.

All four agreements were signed in July 2021, with module shipments expected to commence in February 2022 before completing in September.

Total claims it paid deposit payments totalling US$8.75 million for all four agreements, with the price, volume and delivery schedule all secured.

Total also claims it received assurances from Trina officials that manufacturing capacity for the agreements had been “reserved”.

However Total alleges that on three separate occasions following the signing of the implementation agreements Trina sought to secure additional funds, citing various issues that would change the pricing and delivery schedule of the orders.

Trina is alleged to have issued Total’s subsidiaries with a notice of force majeure on 30 September 2021, confirming that due to the implementation of controls on electricity usage in China at the time, the manufacturer could not produce modules at full capacity. This notice was rejected by Total the following month, Total having claimed that there were insufficient grounds or evidence to declare force majeure.

Between August and October that year Trina is also alleged to have pointed to uncertainty stemming from the initial antidumping and countervailing duty petition filed with the Department of Commerce, which stood to complicate the shipping of solar modules made in Southeast Asia to the US.

This petition was, however, rejected in November 2021, after which Total claims that Trina pointed to the issue of the withhold release order which had meant some shipments of solar goods were being blocked by US Customs and Border Protection.

In late December Trina is alleged to have informed Total that traceability documentation had been approved, however this was swiftly followed by a request for US$40 million in additional payments – on top of the previously negotiated prices – with Trina citing excessive silicon and transport costs.

Total alleges that, to date, Trina has failed to ship any modules under the implementation agreements signed in July of last year, breaching those agreements.

Trina is also alleged to have breached sections of the agreements pertaining to product traceability information, which Total said it has not received.

Total has said it has been forced to pursue alternative procurement arrangements for the four projects in question which has left them delayed and facing higher prices. Total estimates that not only will it face additional costs of around US$100 million due to the non-delivery of modules, but delays to the energisation of the projects has also cost the business in excess of US$100 million.

The case has been filed in California and accuses Trina of promissory fraud, fraudulent inducement and breach of contract, with a fourth cause of action over declaratory relief.

Total is being represented by Los Angeles-based law firm Hueston Hennigan LLP in the case.

Trina Solar issued the following statement to PV Tech in light of the case:

“Trina US has read with concern the reports of a lawsuit being filed against it by Totalenergies and/or its affiliates.  Trina US generally views its customer relationships, and the terms of any supply contracts, as confidential and is extremely disappointed that the Total companies have seen fit to take these matters into the public arena. 

“Based upon its initial review of the allegations made against it (as reported in the press), Trina US strenuously disagrees with Total’s description of events, which are factually inaccurate in numerous respects, as well as legally ill-founded.  Trina US rejects, completely and utterly, any allegation of “breach of contract” or “fraud,” and will vigorously defend its position in the appropriate manner.”

Read Next

Premium
May 20, 2025
PV Talk: At this year’s Intersolar event SEIA's Abigail Ross Hopper said a 'universal effort' would be needed for the energy transition
May 19, 2025
Premier Energies has partnered with Sino-American Silicon Products Inc to establish a 2GW per annum silicon wafer manufacturing facility in India.
May 14, 2025
Solarcycle has signed a recycling agreement with RWE Clean Energy to use its recycling system for 'many' of the latter’s products.
May 14, 2025
Silfab Solar has raised US$110 million through the sale of Section 45X Advanced Manufacturing Production Tax Credits (PTCs).
May 12, 2025
SEG Solar has commissioned the first phase of its newest cell manufacturing facility, in Indonesia, with a production capacity of 2GW.
May 7, 2025
Four leading Chinese PV companies, JinkoSolar, LONGi Green, JA Solar and Trina Solar, recently released their financial reports for Q1 of 2025, all with a decrease in their revenue. 

Subscribe to Newsletter

Upcoming Events

Solar Media Events
May 21, 2025
London, UK
Solar Media Events
June 17, 2025
Napa, USA
Solar Media Events
July 1, 2025
London, UK
Solar Media Events
July 1, 2025
London, UK
Solar Media Events
July 8, 2025
Asia