The continued demand for polysilicon coming primarily from the solar
cell industry has led to WACKER’s starting ‘stage 8’ of polysilicon
production expansion at its Burghausen, Germany site by an additional
7,000 metric tons to a total of 21,500 metric tons per year. 
At a capital cost of around €400 million, the new plant is scheduled to
reach full capacity in 2010 and generate 200 extra jobs directly.

“Today’s
expansion decision reflects the continuously strong demand of our
polysilicon customers,” said Dr. Peter-Alexander Wacker, the Group’s
president and CEO. “We are already the world’s second-largest
polysilicon producer. By heavily increasing our capacities, we intend
to keep narrowing the gap on the market leader. Also, we consider this
project a major contribution to accelerate growth in the solar
industry,” added the CEO.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Thanks to its advanced infrastructure
and integrated production systems, Burghausen proved to be the best
location for this capacity expansion – from both an economic and
technical point of view,” explained Ewald Schindlbeck, President of
WACKER POLYSILICON. “An especially important factor in Burghausen’s
favor,” he added, “is the short time needed to complete the new
facility there.”

First material for sale from the new ‘stage 8’ is expected to be available in Q4 2009.

Read Next

Premium
March 12, 2026
PV Talk: 'The US is entering a pivotal moment for domestic solar manufacturing,' Swift Solar CEO Joel Jean told PV Tech Premium this week.
March 12, 2026
Primergy, launched by Quinbrook Infrastructure Partners, has secured a US$760 million refinancing for its Gemini Solar and Storage Project in Clark County, Nevada.
March 12, 2026
Perovskite-silicon tandem cell manufacturer Swift Solar has acquired manufacturing assets formerly belonging to Meyer Burger.
March 12, 2026
Google has finalised its acquisition of US renewable energy developer Intersect Power, a part of its plan to power its data centre expansions in the US.
March 12, 2026
Trade body the Global Renewables Alliance has called for measures to fast-track the deployment of solar and other renewables amidst the Middle East crisis.
March 12, 2026
Cypress Creek Renewables has acquired the Steel River project in Arkansas from Swift Current Energy, which will come online in 2029.

Upcoming Events

Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain