725MW of Australian solar-plus-storage projects advance in NSW and Queensland

October 21, 2025
Facebook
Twitter
LinkedIn
Reddit
Email
Ark Energy received approval for its Richmond Valley project, which includes plans for a 3.1GWh battery energy storage system. Image: Ark Energy (via LinkedIn).

Australia’s solar-plus-storage sector gained momentum at the end of last week with two project approvals advancing across New South Wales and Queensland, representing a combined 725MW of renewable energy capacity.

The New South Wales (NSW) Independent Planning Commission has granted approval for Ark Energy’s 435MW Richmond Valley solar-plus-storage project, while Global Power Generation advances its 290MW Fraser Coast development through Queensland’s environmental approval process.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Both projects feature substantial battery energy storage components designed to provide extended grid services beyond traditional solar generation, with the Richmond Valley facility incorporating an 8-hour duration battery system.

Ark Energy secures NSW approval for 435MW Richmond Valley solar-plus-storage site

The NSW Independent Planning Commission has granted approval for Ark Energy’s 435MW Richmond Valley solar-plus-storage project in Australia.

The project, located near Rappville in the Northern Rivers region, comprises a 435MW solar PV power plant paired with a 475MW/3,148MWh battery energy storage system (BESS).

The battery component provides 8-hours of storage duration, enabling solar energy dispatch during evening peak demand periods and grid stabilisation services. The facility will occupy 803 hectares of a 1,475-hectare site, approximately 7km east of Rappville, which has a strong history as a timber and beef town.

In March 2025, Ark Energy signed a supply agreement with Seoul-headquartered Hanwha Energy for the BESS technology. The company confirmed it will use lithium iron phosphate (LFP) technology for the BESS.

The company also executed an Early Contractor Involvement agreement with Elecnor Australia in September 2025 to undertake preliminary engineering and design work. The scope includes site studies, detailed engineering design for the solar PV power plant, and balance of plant design for the battery system, with completion expected by Q2 2026.

The project’s 730,000 bifacial solar modules will feature single-axis tracking technology to maximise energy generation throughout the day. The co-located battery system will provide grid services across the National Electricity Market (NEM), including frequency regulation and peak demand management.

Ark Energy received the planning approval last week (16 October) following inclusion of the project in the Federal government’s inaugural Renewable Energy Priority List in March 2025. The Priority List aims to streamline regulatory approvals for significant renewable energy developments and included over 6GW of energy storage.

This article first appeared on Energy-Storage.news as the item ‘Ark Energy bags state approval for 3.1GWh Richmond Valley solar-plus-storage site in Australia’.

GPG advances 290MW Fraser Coast solar-plus-storage project in Queensland

In other news, Global Power Generation (GPG), part of the Naturgy Group, is seeking EPBC Act approval for the Fraser Coast Photovoltaic Solar and Battery Energy Storage System Project, a 290MW solar PV plant featuring a co-located BESS located in Teebar, Queensland, approximately 70km northwest of Gympie.

The solar-plus-storage project will feature approximately 600,000 solar modules installed across a 555.87-hectare site in Teebar. GPG acquired the project area in 2024, and construction is scheduled to commence in late 2025, subject to regulatory approvals and commercial considerations.

The solar PV power plant will connect to the NEM via a 1.3km 275kV transmission line linking the onsite substation to the existing Teebar Substation. The transmission infrastructure will be constructed on land owned by Powerlink Queensland, facilitating the grid integration of renewable energy and storage capacity.

Construction activities will span approximately 14 months and involve site preparation, vegetation clearing, bulk earthworks, and installation of solar arrays, inverters, transformers, and battery storage infrastructure.

The size of the battery energy storage system has not been disclosed in the EPBC Act application; however, GPG’s website states that it will be 180MW/360MWh.

GPG has committed to implementing mitigation measures, including rehabilitation of temporary disturbance areas and ongoing vegetation management during the 30-year operational period.

Solar arrays will be connected to inverter stations and transformers that feed generated electricity into the on-site substation and battery storage system.

GPG has designed the project with end-of-life considerations, including potential repowering with new equipment or decommissioning and site rehabilitation to facilitate the continuation of agricultural land use.

The decommissioning process would involve de-energising and removing all infrastructure, followed by site recontouring, decompaction, and revegetation activities.

This article first appeared on Energy-Storage.news as the item ‘Powerlink Queensland seeks federal approval for AGL’s 2GWh Tuckeroo battery transmission connection’.

Read Next

November 10, 2025
Indian independent power producer (IPP) ReNew Power has secured US$331 million from the Asian Development Bank (ADB) for its solar plant in the Southern state of Andhra Pradesh. 
November 10, 2025
The Australian Renewable Energy Agency (ARENA) will invest up to AU$45 million (US$29 million) in Fortescue's Solar Innovation Hub in the Pilbara region of Western Australia.
November 10, 2025
EnergyCo has shortlisted three consortia to build and operate the transmission network for the New England Renewable Energy Zone (REZ).
November 10, 2025
The Australian government has approved the 300MW Dunmore solar-plus-storage project near Toowoomba, Queensland, completing the environmental assessment process in just 19 days.
November 7, 2025
JA Solar has signed a module supply agreement with EPC contractor Larsen & Toubro (L&T) for two utility-scale projects in Uzbekistan. 
November 7, 2025
Saatvik Green Energy, through its subsidiary Saatvik Solar Industries, secured solar PV module orders worth INR2.99 billion (US$33.7 million). 

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
November 12, 2025
10am PST / 1pm EST
Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal