California rejects another Brightsource CSP project

December 17, 2013
Facebook
Twitter
LinkedIn
Reddit
Email

The California Energy Commission has blocked the construction of Brightsource’s 500MW Palen project.

The Palen Solar Electric Generating System’s (PSEGS) plans involved two CSP towers generating 250MW of energy each.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It is the fourth and final large-scale application in the US. Of those, only its Ivanpah CSP project has been developed.

The commission cited concerns over birdlife following indications that Ivanpah has scorched some passing birds.

“Petitioner argues that an attempt to predict and quantify the project’s potential avian mortality would be improper speculation. However, substantial evidence in the record leads us to the conclusion that avian mortality at the PSEGS project is a virtual certainty,” read the decision published by the commission.

“As of now, the Ivanpah Solar Electric Generating System (ISEGS) project is the only similar power plant using the power tower technology that has been certified by the California Energy Commission and built. To date, ISEGS has not operated at full capacity, but has already resulted in a number of bird deaths. Petitioner has not provided us with sufficient records to calculate a reasonable estimate of avian mortality at PSEGS,” it continued.

The report recommend the conversion of the site, which is on federal land, back to parabolic trough technology. The application by the original applicants for the site, which are now bankrupt, had originally suggested trough technology. The commission also suggested converting the site to a photovoltaic solar farm.

According to the 1000-page document detailing the commissions decision,  Brightsource does not believe either of these options to be economically feasible given the conditions of its financing for the project.

During evidence giving it said: “Though the terms of the PPAs in question are indeed confidential, it can be stated with certainty that the PPAs in question do not allow for a change in technology without the requisite counterparty and CPUC approval, both would be a lengthy and uncertain process.”

The company also said that its interconnection agreement would need be changed which would also be “a lengthy process” and an amendment to either would mean the project could not be established in time to qualify for the Investment Tax Credit, which runs out in 2016.

Read Next

March 20, 2026
Since the start of March, several leading Chinese PV manufacturers have announced overseas module supply agreements.
March 20, 2026
Goldbeck Solar has secured an EPC contract to deliver three PV plants in Poland’s West Pomeranian province, with a combined installed capacity of 722MWp.
March 20, 2026
Renewables developer Newave Energia and investment firm Gerdau have opened a 452MW solar PV plant in Brazil.
Premium
March 20, 2026
SolarPower Europe tells PV Tech Premium of the benefits of a ‘complimentary’ relationship between auctions and corporate PPAs.
March 20, 2026
Danantara, has secured US$1.4 billion to back the government’s push for 50GW of new renewable energy capacity by 2035, with a focus on solar.
March 20, 2026
Global solar PV installations reached 647GW in 2025, up 11% from the previous year, according to data from think tank Ember.

Upcoming Events

Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain