A tale of two Concentrating Solar Power (CSP) Towers generating no electricity?

A funny thing happened on the way to Victorville for the Victor Valley College Solar Power Plant Celebration. I decided to stop in Lancaster, California, to benchmark the eSolar, Inc. CSP project I highlighted earlier this year. As can be seen in my photos over two days, one of the Sierra SunTowers is missing the thermal receiver enclosure nacelle, ample or not, and is out of operation. The second tower has an anemic amount of sunlight focused onto the thermal receiver by the heliostat field although it was late in the day.

When I was taking site photos from the public road next to the solar thermal power plant, a pickup truck left the main gate and stopped to talk. At first I thought my photo taking was going to be discouraged, but it appears to be a common occurrence. Short into our conversation, the driver said: “You should come back when it is lit up.” Prompted by the unseen passenger, the driver added something to the effect the plant had been “lit up” many times before. For example, please see the eSolar press photo below from the 5 MegaWatt (MW) solar plant commissioning in August 2009.

I was flabbergasted at the revelation. Unfamiliar with the technology, my initial suspicions were confirmed. eSolar has said the “Sierra SunTower is the only power tower facility currently operating in North America.” Well, it was not operating on the two consecutive days I visited the site last week. My impression via intuition was the site had been offline for an extended period.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

My “In Search of” eSolar result was all the more surprising given “eSolar’s Sierra SunTower Named Renewable Project of the Year” by Power Engineering and later received the same honor in the 2009 Excellence in Renewable Energy Awards from RenewableEnergyWorld.com, both PennWell publications.

eSolar Founder and Chairman Bill Gross (@bill_gross) likes to tout leveraging “Moore’s law rather than more steel.” I guess Mr. Gross’ misapplication of Moore’s Law does not extend to thermal receivers, pumps, motors, condensers, and turbines?

2010 has been a great year for eSolar beginning with the announcement of a 2 GW (GigaWatt) licensing deal with Penglai Electric in China and the recent award of $10.8 million from the US Department of Energy for CSP baseload system research and deployment testing. However, earlier in May 2010, “PG&E, NRG Change Power Pact To Use Solar Panels, Not Thermal” by Cassandra Sweet for The Wall Street Journal reports on NRG Energy, Inc. (NYSE:NRG) plans to substitute 66 MW of photovoltaic (PV) solar for the prior 92 MW solar thermal contract with PG&E Corporation (NYSE:PCG) based on eSolar technology. The development is striking since NRG Energy is an investor in eSolar and correlates with my recent Sierra SunTower observations.

In the interest of transparency, I call on eSolar to apply basic IT (Information Technology) to dashboard real time operational status and electricity generation from the Sierra SunTower Project on their website. The Sierra SunTower Project points out why O&M (Operations and Maintenance), system uptime, and availability are crucial to reliable CSP generation.

For those looking to visit the site, the exact street address of the eSolar Sierra SunTower Project is 450 W. Ave. G, Lancaster CA 93534. The address has proven difficult to find via Internet search and is not visible yet on the Google maps satellite view.

eSolar has not yet responded to my observations or questions about the operational status of the Sierra SunTower Project although the request was acknowledged.

Of course, I find it ironic I am using Picasa to share my photos of eSolar’s CSP project.

Read Next

July 17, 2024
Germany has been consistently adding over 1GW of solar PV capacity every month since March 2023, and has passed a total of 90GW capacity.
July 17, 2024
From January to May this year, 251 new solar projects became operational in the US, with a combined capacity of 10,669MW.
July 17, 2024
Total global corporate funding for solar on the other hand is down year-on-year, according to Mercom Capital Group.
July 17, 2024
US utility PacifiCorp and rPlus Energies signed a power purchase agreement (PPA) for the Green River Energy Center project in 2022.
July 17, 2024
US-based PV manufacturer Mission Solar Energy has unveiled three new modules aimed at commercial and industrial and utility-scale projects.
Premium
July 17, 2024
Liquidity is rising at great pace in US tax credit transferability for clean energy, helping lenders become comfortable with the market.

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
July 31, 2024
1:00 PM (BST) / 2:00PM (CEST)
Solar Media Events
September 24, 2024
Warsaw, Poland
Solar Media Events
September 24, 2024
Singapore, Asia
Solar Media Events
October 8, 2024
San Francisco Bay Area, USA