First Solar U.S. project pipeline tops 1GW, as thin-film PV company signs 550MW deals with SCE

Facebook
Twitter
LinkedIn
Reddit
Email

First Solar’s U.S. project pipeline now tops the 1GW mark, after the thin-film photovoltaics company and utility Southern California Edison signed deals that will lead to the construction of two large-scale solar power projects in Southern California. The installations in Riverside and San Bernardino counties will have a combined generation capacity of 550MW (AC) of solar electricity, or about 1.2 billion KW-hours, enough to provide power to approximately 170,000 homes, according to SCE.

First Solar will engineer, procure and construct the two solar facilities–the 250MW Desert Sunlight site near Desert Center (to begin in 2012) and the 300MW Stateline project in northeastern San Bernardino county (to begin in 2013)–and equip the power plants with its cadmium-telluride modules. The projects will create hundreds of construction jobs.
 
The agreements must be approved by the California Public Utilities Commission; once network upgrades are done and applicable governmental permits are received, both projects are expected to be finished by 2015.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

California has a goal of delivering 20% of electricity from renewable sources by 2010 and is considering legislation to increase the goal to 33% by 2020. SCE, the leading purchaser of renewable energy in the U.S, said it delivered 12.6 billion KW-hours of energy to its customers from renewable resources in 2008–about 16% of its total energy portfolio. The utility also said it delivered more than 65% of the solar energy produced in the country last year.

First Solar has four other major projects in the pipeline with utility companies in the southwestern U.S., scheduled for completion and activation over the next few years: the 550MW Topaz farm, with PG&E, in central California; the 48MW Copper Mountain site, with Sempra, in southern Nevada; the 30MW Cimarron project, with Tri-State, in northeastern New Mexico; and the 21MW Blythe installation, with SCE, in southeastern California.

Together with the new projects, the company’s total pipeline for the western U.S. has reached 1.199GW (AC). It also has 220MW of sites in development in the Canadian province of Ontario, including a 20MW farm under construction in Sarnia.

During its recent conference call, First Solar said that annualized production capacity at its three manufacturing locations is 1.2GW, with an average line run-rate of 51.7MW per year, module conversion efficiency of 10.9%, and a manufacturing cost per watt of $0.87 cents.

Read Next

August 8, 2025
This week several solar developers have raised funds for projects around the world, including BRUC in Europe, Greenalia in the US, Qair in Mauritius and CREC in Philippines.
August 8, 2025
German solar inverter manufacturer SMA Solar posted losses in the first half of 2025, as demand in the residential and corporate & industrial (C&I) solar sectors 'remains weak'.
August 8, 2025
US solar tracker manufacturer Array Technologies has posted revenue of US$362.2 million in the second quarter of this year.
Premium
August 8, 2025
Energy storage escaped much of the pain inflicted on solar, but foreign entity restrictions may create some supply-chain challenges.
August 8, 2025
Solar PV is likely to become less accessible to low-income Americans after the Environmental Protection Agency (EPA) cancels the US$7 billion Solar For All scheme.
August 8, 2025
Argentinian renewables developer Genneia has reached commercial operations at its 180MW Parque Solar Anchoris in Argentina.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines