Frontier halts 120MW Waroona solar-plus-storage site in Western Australia

Facebook
Twitter
LinkedIn
Reddit
Email
The first stage of the project will feature a 320MWh battery energy storage system (BESS). Image: Frontier Energy.

Renewable energy developer Frontier Energy has halted developing its 120MW solar-plus-storage project in Western Australia after it missed out on Reserve Capacity Credits (RCCs) from the Australian Energy Market Operator (AEMO).

The Waroona Renewable Energy Hub’s first stage would feature a 120MW solar PV power plant along with an 80MW/360MWh DC-coupled battery energy storage system (BESS). Once fully completed, Frontier said it would be one of Australia’s largest renewable energy projects, with a 1GW connection capacity.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Waroona was provisionally assigned 87.2MW of Certified Reserve Capacity in August 2024, but Frontier missed out on securing RCCs in the final allocation process.

The Reserve Capacity Mechanism (RCM), which encompasses RCCs, ensures sufficient generation capacity in the South West interconnected system (SWIS). Generators in the Wholesale Electricity Market (WEM) receive a fixed dollar payment per megawatt from the AEMO based on the Reserve Capacity Price (RCP). These payments would be guaranteed for five years.

A Definitive Feasibility Study (DFS) conducted by Frontier for the Waroona project estimated that RCM payments would provide up to AU$27 million (US$18.6 million) per annum of revenue in the project’s first stage. As such, Frontier employed a five-year strategy for the Waroona project, which factored in AEMO’s forecast of a ~1GW reserve capacity deficit in 2026/2027.

AEMO also said there was an urgent need for substantial new investment in generating capacity.

This article was first published on our sister site Energy-Storage.news.

Read Next

July 10, 2026
Australia and India have formalised a broadened energy partnership that spans renewable energy deployment, supply chain resilience, critical minerals, rooftop solar training and uranium exports.
July 9, 2026
India added approximately 26GW of solar capacity and 3GW of wind capacity during the first half of 2026, according to JMK Research. 
July 9, 2026
The latest Silicon Industry Branch figures indicate continued weakness in the Chinese polysilicon market this week, though the decline slowed markedly.
July 9, 2026
Premier Energies expects to begin construction of the first phase of its planned 10GW ingot and wafer manufacturing facility in Andhra Pradesh shortly.
July 9, 2026
Uri Sadot provides an explanation of the cybsersecurity situation for European solar, and what action asset owners must take to comply with NIS2.
July 9, 2026
India's power transmission sector is set for a multi-year investment cycle between FY2027 and FY2032, according to ICRA.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye