India tenders 70GW of renewable energy in FY 2024, half from solar PV

Facebook
Twitter
LinkedIn
Reddit
Email
Chart of India's utility-scale renewable energy tendered in the past fiscal years
Despite a decrease in the price of solar modules, solar tariffs have gone up in the past two years. Chart: IEEFA.

India has more than trebled utility-scale renewables tender capacity to 69.8GW in fiscal year 2024, 48% of which from solar PV.

Out of the nearly 70GW of capacity tendered from 1 April 2023 until 31 March 2024, 40GW ended up being awarded, according to a report from the Institute for Energy Economics and Financial Analysis (IEEFA) and JMK Research & Analytics. This represents a fourfold increase from FY23 when only 10GW of capacity ended up allotted, while the capacity tendered in FY24 surpassed the government’s target of 50GW. It is expected that for FY25, tenders will again surpass the 50GW government threshold, with awarded capacity to further increase.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Solar tariffs have increased marginally by nearly 8.5% in the past two years, from an average of INR2.3-24/kWh (US$0.027-0.0287/kWh) to INR2.5.26/kWh, despite module prices decreasing by 57% during the same period.

A quarter of the nearly 70GW of renewable capacity tendered came from Indian utility Solar Energy Corporation of India (SECI), highlighting the importance of state-level tendering authorities’ role in the deployment of utility-scale renewables.

Since the introduction of hybrid tenders in 2018, solar-wind hybrid share has increased from 16% in FY20 to 43% in FY24, while solar as a standalone accounted for nearly half of all capacity tendered during FY24.

“There is strong investor interest in the Indian utility-scale renewable energy market. The primary reasons are the large-scale potential for market growth, central government support in terms of targets and regulatory frameworks, and higher operating margins,” said, Vibhuti Garg, Director – South Asia at IEEFA and contributing author of the report.

Despite the increased capacity tendered and awarded during FY24, challenges still persist in the execution of the tenders.

Chief among them are the 40% import duties on solar modules introduced with the basic customs duty in April 2022 and the requirement to procure domestically-manufactured components, through the Approved List of Models and Manufacturers (ALMM). The ALMM was recently reinstated after a one-year moratorium due to an inadequate supply of domestic-made components.

According to the report, India had 68GW and 8GW of module and cell annual nameplate capacity, respectively, as of April 2024. However, actual production capacity is much lower with only 17GW of module shipments in 2023 by Indian manufacturers.

Moreover, over 10 new developers entered the Indian utility-scale market in the past couple of years, including US independent power producer BrightNight who partnered with energy platform ACEN Corporation to ramp up the development of its 1.2GW renewables portfolio in India.          

Read Next

September 10, 2025
Indian solar module manufacturer Vikram Solar reported a 79.7% year-on-year increase in revenue for the first quarter of FY26.
September 8, 2025
France has awarded 971MW of ground-mount solar capacity, to 165 projects, in the eighth round of the PPE2 PV tender.
September 8, 2025
Vikram Solar has won a 336MW module supply agreement from L&T Construction for the 2.3GW Khavda solar park in Gujarat. 
September 4, 2025
India’s Goods and Services Tax (GST) Council, the joint forum of the Centre and States, has reduced the GST rate on renewable energy components from 12% to 5%. 
September 4, 2025
Indian solar manufacturer Waaree Energies has acquired a 64% equity stake in power transformer manufacturing company Kotsons.
September 3, 2025
India has added 2.8GW of rooftop solar in H1 2025, a 158% year-on-year surge from just 1.1GW in the same period last year.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines