Maryland denies permits for Origis Energy’s 32.5MW PV project

Facebook
Twitter
LinkedIn
Reddit
Email
The solar plant would have powered 49% of Georgetown’s electricity load for campus operations. Image: John Weiss / Flickr

Maryland’s Department of the Environment (MDE) has denied a wetlands and waterways permit to Origis Energy’s 32.5MW PV project in La Plata, Charles County, Maryland.

The project drew criticism for its potential effects on the local ecosystem, with the Baltimore Sun reporting that more than 97 hectares of forest would have to be cleared in order to make room for the new installation. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Back in 2018, the Maryland Public Service Commission approved the project, but brushback from environmental activists and local residents prompted another review by Maryland environment officials. 

Maryland’s Department of the Environment also denied a permit for another Origis Energy project, the proposed 27.5MW Ripley Road solar installation.

Maryland Environment Secretary Ben Grumbles said in a statement announcing the denial of the permit: “While Maryland strongly supports the increased use of clean and renewable energy sources, these two proposed projects would harm the nearby high-quality stream in Charles County and threaten our continued restoration progress in the Chesapeake Bay watershed. This is an unacceptable trade-off for the environmental benefits of clean energy. Maryland will continue to be a leader on clean and renewable energy that makes sense for our local communities and environment.”

The 32.5MW Shugart Valley project was denied its permit after the MDE determined that “the applicant failed to document and demonstrate that a serious effort was made to avoid, minimize and mitigate or otherwise offset the effects on water quality. Additionally, MDE does not consider the economic or social benefits of the proposed project to justify any decrease in water quality.”

The Shugart Valley project was originally slated to be completed this summer, with the installation expected to generate approximately 75,000 MWh of power annually and power 49% of Georgetown’s electricity load for campus operations located in Washington, D.C. It would have been comprised of 105,000 solar panels and would have created 200 jobs during its construction phase. 

Read Next

August 19, 2026
Japanese PV manufacturer Toyo has reported 2.6GW of cell shipments and 191.5MW of module shipments in the first half of 2026.
August 19, 2026
Dimension Energy has secured US$857 million in additional capital to expand its distributed solar platform across 29 projects in the US.
August 19, 2026
US-based module manufacturer Translucent Solar has entered production ramp-up at its module assembly plant in South Carolina.
August 19, 2026
EDF power solutions North America has signed two PPAs with NV Energy to sell power generated at a solar-plus-storage project in Nevada.
August 19, 2026
A patent infringement lawsuit filed by Maxeon against Canadian Solar has been dismissed with prejudice in the US Federal District Court.
August 18, 2026
Tax credit transfer value in the US rose between the second half of 2025 and the first half of 2026, according to Crux.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye