Bids of US$0.0162/kWh emerge as Saudi Arabia shortlists firms for 1.47GW solar tender

April 6, 2020
Facebook
Twitter
LinkedIn
Reddit
Email
The round-two tendering of 1.47GW of solar comes after round one delivered the 300MW Sakaka project. Image credit: Huawei

Some of the world’s top green energy players have tabled ultra-low bids under the second round of Saudi Arabia’s renewable energy programme, set to contract a 1.47GW all in all.

The kingdom's Renewable Energy Project Development Office (REPDO) recently identified the firms and consortia shortlisted to develop a slew of solar projects across the country, with some proposing tariffs below the 2-US-dollar-cent-per-kWh threshold.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

At 600MW in planned capacity, the Al-Faisaliah PV project is the largest of the lot and will be either contracted to a consortium led by Saudi player ACWA Power, or a rival partnership led by United Arab Emirates-headquartered firm Masdar.

According to REPDO, the bids for Al-Faisaliah from either side were “extremely close”. The gap between the figures for levelized costs of electricity (LCOE) each had produced was, the government agency said, “within statistical margin of error”.

REPDO’s next step for the 600MW project will be to have the two consortia compete under a ‘best and final offer’ approach. The tendering results for this particular project will be revealed at some point in April 2020, the Office added.

The agency did shed light on the tariffs proposed for every other project under the round-two tender. From ACWA to First Solar, Marubeni and others, the shortlisted bidders (see table below) proposed a wide range of prices for PV schemes in the 20MW-300MW spectrum.

Shortlisted solar tariffs under Saudi Arabia’s NREP (round two)

Project name (capacity) Jeddah PV IPP (300 MW) Rabigh PV IPP (300 MW) Qurrayat PV IPP (200 MW) Madinah PV IPP (50 MW) Rafha PV IPP (20 MW)
Shortlisted bidder #1 (tariff offered in US$) Masdar-led consortium (US$0.0162/kWh) Marubeni-led consortium (US$0.017/kWh) ACWA-led consortium (US$0.0178/kWh) Al Blagha-led consortium (US$0.019/kWh) Al Blagha-led consortium (US$0.0348/kWh)
Shortlisted bidder #2 (tariff offered in US$) ACWA-led consortium (US$0.0165/kWh) ACWA-led consortium (US$0.0175/kWh) Total Solar-led consortium (US$0.018/kWh) First Solar-led consortium (US$0.0302/kWh) First Solar-led consortium (US$0.05/kWh)
Source: REPDO

PV rounds of 1.47GW and 1.2GW for oil-reliant kingdom

Held under the so-called National Renewable Energy Program (NREP), Saudi Arabia’s tenders are part of a plan to drive a renewable boom in the space of a decade. Previously floated targets would have the country reach major volumes of installed solar (40GW) and wind and others (20GW) by 2030.

The country – which relies on oil revenues to prop up national budgets – has recently seen sharp declines in reference barrel prices, as lockdown plans enacted due to the COVID-19 crisis forced downwards revisions of demand for the fossil fuel.

Analysts believe however that solar growth will be forthcoming, amid predictions the country will be one of a few global “growth engines” – installing 1-GW of PV every year – by 2024. NREP’s round-one already delivered the 300MW Sakaka PV plant, while round-three is set to unlock a further 1.2GW.

Winners of the NREP scheme will be rewarded with a 25-year PPA, featuring the Saudi Power Procurement Company (SPPC) as offtaker. In return, their solar installations will have to comply with a minimum 17% share of local content, as defined under Saudi law.

The solar bids of US$0.0162/kWh now being touted in Saudi Arabia mirror the tariffs of US$0.016953/kWh scored last October by a 900MW project in Dubai. The Middle Eastern solar milestones emerge after similar numbers were reported for PV tenders in Brazil and Portugal.

The Middle East has become a sought-after target among Asian solar makers, keen to supply an area seen as lacking domestic manufacturing firepower. From Huawei to Jolywood, Chinese players recently walked PV Tech (see links ahead for part one and two) through their moves in the region.

Read Next

October 24, 2025
US solar tracker manufacturer Nextracker and Saudi-based energy company Abunayyan Holding have formed a joint venture (JV) in Saudi Arabia.
October 24, 2025
The Saudi state-owned renewables developer Masdar has begun construction on a giant solar-plus-storage project in Abu Dhabi.
October 23, 2025
Solar PV technology has maintained its leading position as the most cost-competitive power generation source in 2025, according to analyst Wood Mackenzie.
October 20, 2025
Bahrainian authorities are inviting initial proposals from developers to build a 100MW solar project in the country, due for commercial operation by September 2027.
October 16, 2025
Masdar and Turkey have entered the final stage of US$1 billion agreement to develop the 1.1GW plant in Bor, Niğde Province, central Turkey.
October 13, 2025
France’s Engie and the UAE’s Masdar have been chosen to jointly develop a 1.5GW PV power plant near Abu Dhabi.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 10, 2026
Frankfurt, Germany
Solar Media Events
March 24, 2026
Lisbon, Portugal