Exclusive: Japan considering FiT cancellation for unbuilt PV projects

October 7, 2013
Facebook
Twitter
LinkedIn
Reddit
Email

Sanctions including the withdrawal of feed-in tariff (FiT) certification are being considered by the Japanese government for PV projects that have been approved under the country’s FiT but remain unbuilt, PV Tech has learned.

Japan’s Ministry of Economy, Trade and Industry (METI) has launched an investigation into why only around 10% of large-scale PV projects approved under the FiT have so far been connected to the grid system.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

A survey expected to last around a month was launched on 22 September examining projects larger than 400kW capacity. METI said the investigation was a “fact-finding” survey to establish why such a small proportion of approved projects had been completed.

Various reasons have been cited for the lack of movement, including grid connection problems – Japan has a regionally demarcated grid system, with 10 different companies responsible for the grid in different areas. Hokkaido, the largest of the island territories to the north of Japan where land is in relatively abundant supply, is unable to connect more than about one in four approved projects to the grid due to connection problems and oversupply.

But METI suspects other factors are at play, including developers deliberately delaying projects in the hope that equipment costs will come down.

Speaking to PV Tech, Takashi Kitamura of the New Energy Policy Division at METI’s Agency for Natural Resources and Energy Conservation and New Energy Department, acknowledged that a large number of projects remained unbuilt.

Explaining that because once a project has been approved by the government and then by the utility company responsible for the corresponding section of grid, developers must then evaluate their own costs before breaking ground, Kitamura said it was possible that companies may then decide to wait on falling equipment prices before beginning construction, in order to improve profit margins.

Kitamura also said he had heard anecdotal, but as-yet unsubstantiated rumours, that some companies may be brokering deals to effectively subcontract projects out to smaller developers.

Describing the current investigation as a “fact-finding survey”, Kitamura said METI would consider what measures should be taken once the survey was completed. It is scheduled to finish on 18 October. The survey would be taking into account the situation of each company involved in project development and asking each for details including the state of finances, he said.

PV Tech understands that the survey will seek to define the status of individual projects and the willingness of developers to give up unbuilt projects.

Those developers that are unwilling to give up projects but have not yet started building them will be asked to report on when they plan to begin construction.

They will also have to provide documentation proving they have ordered components and evidence of land purchase or lease agreements. Until December 2012 a project could receive approval without land purchase or lease agreements, and this is thought to be another possible factor behind the high number of unbuilt projects.

But it appears that METI is keen to not rush to judgement. Kitamura said the survey may find that some companies had simply run out of resources or were otherwise unable to finish projects in unfortunate circumstances despite the will to continue.

However if it was the case that projects were intentionally delayed or corruption had taken place, Kitamura said METI would then have no choice but to consider what measures were to be taken. 

While he stressed that METI would not announce or consider enacting any possible punitive measures until survey data was collated, if it was found to be beyond doubt that developers or investors were intentionally stalling on projects, various sanctions could be considered.

This could ultimately include revoking certification given under the FiT scheme, although again Kitamura was at pains to emphasise that the outcome would depend on the full results of the survey.

Additional reporting by Ben Willis.

Read Next

Premium
January 30, 2026
In an interview with PV Tech Premium, two UNSW researchers emphasise the need for enhanced UV testing for TOPCon solar cells.
January 29, 2026
Canadian renewables firm Westbridge Renewable Energy has received approval from the Alberta Utilities Commission (AUC) to build an up to 225MW solar-plus-storage plant in Alberta, Canada.
January 29, 2026
Enfinity has started commercial operations at a 33.8MW solar PV project, the first in a portfolio from which Microsoft will acquire power
January 29, 2026
The cost of Chinese solar module manufacturing will rise in the first half of 2026, though prices may fall again before the end of the year.
January 29, 2026
PV module defects are increasing as manufacturers struggle to achieve consistent quality through robust bill-of-material and process controls.
January 29, 2026
A Korean-led consortium including Hyundai Engineering has started construction at a 350MW solar PV plant in Dallas, Texas.

Upcoming Events

Solar Media Events
February 3, 2026
London, UK
Upcoming Webinars
February 18, 2026
9am PST / 5pm GMT
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA