The project at the Hearst cattle ranch is first to use the firm's new Series 6 modules. Source: Hearst.

The 280MW California Flats project has reached commercial operation, with First Solar’s large format Series 6 modules sending power to the grid for the first time at this scale.

The site was developed by First Solar before asset management firm Capital Dynamics bought it in August 2017.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The California Flats Solar Project is also the first to feature our innovative Series 6 PV module technology, which is setting the standard for affordable and cleaner renewable energy,” said Troy Lauterbach, senior VP of EPC and Energy Services for First Solar. “We are thrilled to partner with Capital Dynamics and Hearst to deliver on a shared commitment to building a sustainable energy future,” he added.

The site is part of the Hearst cattle ranch, which provides beef to Whole Foods.

Power from the site is sold to utility and commercial customers under two long-term power purchase agreements (PPA).

“The California Flats Solar Project helped us meet our goal of finding a sustainable solution to keep the 73,000-acre Jack Ranch intact as a historic working cattle ranch using traditional and time-proven ranching methods for our grass-fed Hearst Ranch Beef program,” said Steve Hearst, Vice President and GM of Hearst Western Properties.

“Countless hours have been invested by Hearst and our partners in bringing this sizable, complex project to fruition and ensuring it operates seamlessly with our cattle operation and ranch environment,” he added.

Read Next

Premium
November 6, 2026
PV Tech spoke with many industry experts about the midterm election results, covering topics such as permitting, state-level impact and investment appetite.
November 6, 2026
US tracker manufacturer FTC Solar has registered revenues of US$32.8 million in the third quarter of 2026, up both sequentially (25.4%) and year-on-year (26.1%).
November 6, 2026
A New South Wales (NSW) parliamentary inquiry has recommended that data centres be legally required to supply their own 100% renewable energy on an hourly basis, a stricter test than the state's current guidelines.
November 5, 2026
Sunrun reports 5GWh of networked storage capacity in the third quarter of 2026, while solar additions reached 204MW.
November 5, 2026
Essar Renewables has signed a PPA with NHPC Limited for a 300MW firm and dispatchable renewable energy (FDRE) project in Andhra Pradesh.
November 5, 2026
Independent power producer (IPP) Energix Renewables has brought its 152MWdc Border Basin solar project online in Hancock County, Ohio, with the facility now delivering power to the PJM Interconnection market.