Solar park infrastructure delay causes India’s NTPC to retender 250MW in Karnataka

Facebook
Twitter
LinkedIn
Reddit
Email
Concerns around major solar tenders being carried out before solar park infrastructure has been completed had been aired for some time. Flickr: Vinoth Chandar

Indian utility NTPC has retendered 250MW of PV at a solar park in Karnataka after infrastructural issues at the park dampened the interest of developers to participate.

Consultancy firm Mercom Capital Group reported an NTPC official saying that infrastructure is now complete at the Pavagada Solar Park in Tumkur district. Mercom also said that a new benchmark tariff of INR4.51 (US$0.066) set by Karnataka Electricity Regulatory Commission (KERC) may have contributed to the reluctance among developers.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The capacity was first tendered back in February 2016, while another 250MW was tendered in September that year. Once again projects will be divvied out in five blocks of 50MW each and will come under the Domestic Content Requirement (DCR) that mandates cells and modules to be sourced from local manufacturers.

The tender requires design, engineering, manufacturing, supply, packing and forwarding, transportation, unloading, storage, installation and commissioning. It also requires O&M services for a period of five years.

Last week, NTPC also retendered another 750MW at the park in the open category.

Mercom has previously reported that solar development in India has been held back by delays in preparing the 20GW of solar park capacity planned by the central government. Concerns around major solar tenders being carried out before solar park infrastructure has been completed had been aired for some time and developers have faced poor accessibility to certain parks and a lack of clarity around land allocations.

Read Next

May 30, 2025
Waaree Solar Americas – a subsidiary of Indian solar manufacturer Waaree Energies – has signed a 586MW solar module supply agreement with an undisclosed independent power producer (IPP).
May 29, 2025
Singapore-based engineering firm Sembcorp has received a letter of award from Indian public sector power company SJVN for 150MW of solar power and a 300MWh battery energy storage system (BESS).
Premium
May 29, 2025
PV Talk: Global Solar Council CEO Sonia Dunlop tells Shreeyashi Ojha why the solar industry needs collective action to combat political and supply-chain disruption.
May 28, 2025
The expansion is 100% compliant with the Indian government's requirement of Bureau of Indian Standards (BIS).
May 27, 2025
India has shipped 12.5GW of module capacity in the first quarter of 2025, according to data from energy consultancy JMK Research.
May 20, 2025
Solar PV additions have slowed down in the first quarter of 2025 in India, with 6.7GW, according to a report from Mercom India Research.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
June 17, 2025
Napa, USA
Upcoming Webinars
June 30, 2025
10am PST / 6pm BST
Solar Media Events
July 1, 2025
London, UK
Solar Media Events
July 1, 2025
London, UK
Solar Media Events
July 8, 2025
Asia