Solar park infrastructure delay causes India’s NTPC to retender 250MW in Karnataka

Facebook
Twitter
LinkedIn
Reddit
Email
Concerns around major solar tenders being carried out before solar park infrastructure has been completed had been aired for some time. Flickr: Vinoth Chandar

Indian utility NTPC has retendered 250MW of PV at a solar park in Karnataka after infrastructural issues at the park dampened the interest of developers to participate.

Consultancy firm Mercom Capital Group reported an NTPC official saying that infrastructure is now complete at the Pavagada Solar Park in Tumkur district. Mercom also said that a new benchmark tariff of INR4.51 (US$0.066) set by Karnataka Electricity Regulatory Commission (KERC) may have contributed to the reluctance among developers.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The capacity was first tendered back in February 2016, while another 250MW was tendered in September that year. Once again projects will be divvied out in five blocks of 50MW each and will come under the Domestic Content Requirement (DCR) that mandates cells and modules to be sourced from local manufacturers.

The tender requires design, engineering, manufacturing, supply, packing and forwarding, transportation, unloading, storage, installation and commissioning. It also requires O&M services for a period of five years.

Last week, NTPC also retendered another 750MW at the park in the open category.

Mercom has previously reported that solar development in India has been held back by delays in preparing the 20GW of solar park capacity planned by the central government. Concerns around major solar tenders being carried out before solar park infrastructure has been completed had been aired for some time and developers have faced poor accessibility to certain parks and a lack of clarity around land allocations.

Read Next

September 12, 2025
ACME Venus Urja has secured INR3.8 billion (US$43 million) to develop and construct a solar-plus-storage project in Barmer, Rajasthan.
September 10, 2025
Indian solar module manufacturer Vikram Solar reported a 79.7% year-on-year increase in revenue for the first quarter of FY26.
September 8, 2025
Vikram Solar has won a 336MW module supply agreement from L&T Construction for the 2.3GW Khavda solar park in Gujarat. 
September 4, 2025
India’s Goods and Services Tax (GST) Council, the joint forum of the Centre and States, has reduced the GST rate on renewable energy components from 12% to 5%. 
September 4, 2025
Indian solar manufacturer Waaree Energies has acquired a 64% equity stake in power transformer manufacturing company Kotsons.
September 3, 2025
India has added 2.8GW of rooftop solar in H1 2025, a 158% year-on-year surge from just 1.1GW in the same period last year.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines