Solar park infrastructure delay causes India’s NTPC to retender 250MW in Karnataka

Facebook
Twitter
LinkedIn
Reddit
Email
Concerns around major solar tenders being carried out before solar park infrastructure has been completed had been aired for some time. Flickr: Vinoth Chandar

Indian utility NTPC has retendered 250MW of PV at a solar park in Karnataka after infrastructural issues at the park dampened the interest of developers to participate.

Consultancy firm Mercom Capital Group reported an NTPC official saying that infrastructure is now complete at the Pavagada Solar Park in Tumkur district. Mercom also said that a new benchmark tariff of INR4.51 (US$0.066) set by Karnataka Electricity Regulatory Commission (KERC) may have contributed to the reluctance among developers.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The capacity was first tendered back in February 2016, while another 250MW was tendered in September that year. Once again projects will be divvied out in five blocks of 50MW each and will come under the Domestic Content Requirement (DCR) that mandates cells and modules to be sourced from local manufacturers.

The tender requires design, engineering, manufacturing, supply, packing and forwarding, transportation, unloading, storage, installation and commissioning. It also requires O&M services for a period of five years.

Last week, NTPC also retendered another 750MW at the park in the open category.

Mercom has previously reported that solar development in India has been held back by delays in preparing the 20GW of solar park capacity planned by the central government. Concerns around major solar tenders being carried out before solar park infrastructure has been completed had been aired for some time and developers have faced poor accessibility to certain parks and a lack of clarity around land allocations.

Read Next

August 6, 2025
The Indian Ministry of New and Renewable Energy (MNRE) has published the approved list of models and manufacturers (ALMM) for solar cells, which contains 13GW of annual nameplate capacity across six manufacturers.
August 4, 2025
Indian solar PV module manufacturer Vikram Solar will supply 250MW of n-type modules to Bondada Group for its solar project in Maharashtra.
August 4, 2025
Waaree Energies has commissioned a 1.8GW solar module manufacturing line at its factory in Chikhli, Navsari district, Gujarat.
July 30, 2025
Donald Trump has announced a 25% tariff on all imports entering the US from India from the 1st August 2025.
July 29, 2025
US-based solar manufacturer T1 Energy has expressed support for the US government’s tariff investigations into global polysilicon imports and solar products from Laos, Indonesia and India.
July 25, 2025
A round-up of news from the Indian solar sector this week, including Reliance Industries' cell plant, Juniper Green Energy powering solar PV and Solex Energy launching new modules.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines