PJM fast-tracking interconnection plan could favour gas-fired plants over renewables

Facebook
Twitter
LinkedIn
Reddit
Email
The selected projects could save at least 18 months of development time. Image: Gerry Machen via Flickr.

The US Federal Energy Regulatory Commission (FERC) has approved the PJM Interconnection’s proposal to fast-track up to 50 projects, which could favour gas-fired power plants over renewables.

According to environmental organisation Sierra Club this decision could also increase the costs for renewable energy sources that are in the PJM interconnection queue, some of which have been waiting for a grid connection for over six years.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In response to the FERC decision, Megan Wachspress, staff attorney at Sierra Club, said: “The Sierra Club has advocated tirelessly for PJM to expedite its interconnection process to get more renewable energy online, which would lower energy costs for its millions of customers and reduce pollution across 13 states.

“PJM is still resisting reforms and has legally challenged a FERC order that would speed up the interconnection process.”

Non-profit environmental advocacy group the Environmental Law & Policy Center (ELPC) raised similar concerns which were included in FERC’s order, accessible here.

ELPC argued that PJM’s scoring system would favour specific resource classes, such as combined cycle gas, that “have electricity generation attributes that PJM prefers”.

This is despite gas-fired power plants representing only 6% of the total capacity in the PJM interconnection queue. Solar PV alone represented nearly 150GW of interconnection queue – numbers for PJM only – at the end of 2023, according to Lawrence Berkeley National Lab’s yearly report on queued-up capacity in the US, which was published last year.

One-time initiative adding at least 10GW of capacity

PJM’s fast-track interconnection plan would be implemented through a one-time Reliability Resource Initiative (RRI) for projects that are “shovel ready” and were already in the queue. It will further accelerate the development of these 50 projects which could save at least 18 months.

The application window for projects under RRI will open on 28 February and closes on 14 March 2025. The RRI process is open to generation interconnection requests from all types of resources with a minimum 10MW of unforced capacity (UCAP) with no limits in terms of applications.

PJM said that the proposals will be scored according to market impact criteria – UCAP, Effective Load Carrying Capability and zonal need – and commercial operation date viability.

In its decision, the FERC Commission argued: “We find that the proposal reasonably addresses the possibility of a resource adequacy shortfall driven by significant load growth, premature retirements, and delayed new entry.”

This shortfall of capacity, mentioned by the FERC Commission, could sum up to a 10GW gap by 2030/2031 and even up to 26GW gap depending on a 2025 forecasted load growth analysis, according to the FERC order. A study from PJM stated that by 2030 up to 40GW of existing installed capacity could be retired.

“This one-time initiative should provide a much-needed on-ramp to the reliability of the PJM system in the short term as we continue to move existing queued projects through our transition cycles,” said Chris O’Hara, senior VP and general counsel at PJM. “We now hope to see suppliers take advantage of this unique opportunity.”

Moreover, this one-time initiative comes as PJM’s ongoing reform of its interconnection process aimed to be more efficient and changing from a first-come, first-served queue process to a first-ready, first-served approach.

Started in July 2023 and still ongoing, the interconnection process reform aims to process over 200GW in generation projects across all technologies by 2026, when it expects to complete said process. Currently, there are already 50GW of projects that have gone through the PJM study process which are ready for construction, interconnection and operation, according to PJM.

The Regional Transmission Organisation (RTO) covers 13 states – including Pennsylvania, Virginia, New Jersey and Michigan among others – in the north-east of the US and the District of Columbia.

16 June 2026
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 16-17 June 2026, will be our fifth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2028 and beyond.
13 October 2026
San Francisco Bay Area, USA
PV Tech has been running an annual PV CellTech Conference since 2016. PV CellTech USA, on 13-14 October 2026 is our fourth PV CellTech conference dedicated to solar manufacturing in the USA. From polysilicon, wafers, ingots, cells and modules, to critical component suppliers including glass and frames, the event connects every stage of the value chain under one roof. PV CellTech USA also brings together investors, innovators, manufacturers and industry stakeholders to collaborate and strengthen domestic solar manufacturing across the United States.

Read Next

Premium
May 22, 2026
PV Talk: Frank Oudheusden explains how robotics could create a paradigm shift and improvements in PV system optimisation for extreme weather.
May 22, 2026
The planned merger of US utilities NextEra Energy and Dominion Energy should be met with “caution” by state lawmakers, according to a number of US clean energy and political non-profit groups.
May 22, 2026
Polar Racking has launched a Solar Asset Management Division to support operations and maintenance (O&M) activities across utility-scale and commercial solar projects in North America and the Caribbean. 
May 21, 2026
US solar glass producer Stewart Glass is expanding its facility in Ohio with a new production line expected in 2027.
May 21, 2026
Spanish independent power producer Grenergy has signed a long-term hybrid power purchase agreement (PPA) with US utility Georgia Power.
May 20, 2026
Canadian energy firm Enbridge will develop a 365MW/1,600MWh solar-plus-storage project in Wyoming, US, as part of an ongoing partnership with tech and data giant Meta.

Upcoming Events

Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Media Partners, Solar Media Events
June 2, 2026
Johannesburg, South Africa
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA