Polysilicon supply chain issues emerging as spot prices rise, says Barclays Capital

Facebook
Twitter
LinkedIn
Reddit
Email

Just when it was safe to say that the severe polysilicon shortages from a few years ago were long-gone and that a era of oversupply boded well for users in the solar industry, issues have emerged within the supply chain that are forcing spot prices higher once again. According to a report from Barclays Capital financial analyst, Visal Shah, checks have shown that spot prices have risen to as high as US$70-80/kg, yet spot prices were at US$55-60/kg range, only a few weeks ago. Bottlenecks were said to have appeared from polysilicon through to wafering, according to the analyst.

Shah noted in his investor note that there were several issues most likely affecting spot prices at the moment. There have been polysilicon supply issues due to production halts due to technical problems such as fires at LDK’s polysilicon plant, which Shah said had meant the plant needed to be shutdown recently.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

This had led to LDK attempting to secure as much polysilicon for its wafer production operations due to strong demand for wafers.

Another producer in China, Xinguang had shut operations completely, while it worked to replace old production equipment and systems originally supplied from Russia to modern technology that would enable the company to compete better in the future. Barclays Capital said Xinguang’s capacity before the shutdown had been 1,200MT/yr.

The well documented recent power outage at an REC run plant was also cited as a catalyst behind polysilicon shortfalls and higher demand for spot polysilicon.

However, the report also links capacity mismatch issues at the wafer and cell segment of the supply chain notably that checks has shown that ingot capacity currently exceeded wire saw capacity, which remained ‘tight.’

In periods of high-demand for wire saw systems, lead times can extend considerably due to the complexity of the machines and set-up times before entering production. Although key equipment suppliers such as Meyer Burger and Applied Materials HCT arm have added capacity over the last few years to meet the last major wave of orders, the current wafer capacity additions are on a completely different scale than those seen in 2007 and 2008.

Barclays Capital noted that one customer of Applied Materials HCT arm had equipment scheduled originally for delivery in February, 2010 but received the order five months later.   

Although common practice to multiple-source wafering equipment, demand for equipment is high and difficult to find suppliers without supply constraints as all equipment is usually made to order.

Shah also noted that there had been an overall higher than anticipated wafer and cell capacity additions in July to August timeframe yet manufacturers were unable to obtain polysilicon, especially on the spot market.

Shah believes that most polysilicon suppliers have contracted nearly 100% of the volumes to long term contracts in order to avoid the sharp swings in spot market, leaving suppliers unable to fulfil increased demand from the spot market, despite attractive prices.

Read Next

July 15, 2026
Qualitas Energy has secured a €53 million (US$63 million) non-recourse financing package for a 117MWp greenfield solar PV portfolio in Poland.
July 15, 2026
US IPP Cypress Creek Energy has started construction work at its Steel River Energy Center in Arkansas, which will include 2.5GW of solar PV and sell power to tech giant Google.
July 15, 2026
CERC issues suo motu order to release interstate transmission connectivity reserved for renewable projects that failed to secure PPAs.
July 15, 2026
Global Infrastructure Partners (GIP), a subsidiary of global asset owner giant BlackRock, has agreed to acquire a majority and controlling interest in commercial solar PV developer Summit Ridge Energy.
July 15, 2026
Avantus has signed a 20-year PPA with the Clean Power Alliance (CPA) in California for the output of a 200MW solar-plus-storage project.
July 14, 2026
Masdar has reached financial close on what it called the world’s .first gigascale 24/7 renewable energy project'.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye