Powerlink Queensland seeks federal tick for substation to connect 775MW solar PV plant

October 23, 2025
Facebook
Twitter
LinkedIn
Reddit
Email
Genex’s 50MW Kidston Solar Project in Queensland. Image: Genex Power.

Powerlink Queensland is seeking federal approval to expand its existing 330kV Bulli Creek Substation in Southern Queensland to accommodate the grid connection of Genex Power’s 775MW Bulli Creek solar PV power plant.

The expansion has been submitted to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The substation expansion will be a critical piece of transmission infrastructure, enabling one of Australia’s largest solar developments to deliver renewable energy into the National Electricity Market (NEM).

Currently, the existing Bulli Creek Substation lacks sufficient capacity to accommodate the solar plant’s connection, necessitating the expansion project to enable grid integration of the renewable energy facility located approximately 6km south of the substation.

According to the EPBC Act application, the substation expansion encompasses a 27-hectare study area located entirely on Powerlink freehold land. Construction activities are confined to a 4.3-hectare disturbance footprint representing the maximum direct impact area.

The study area borders Western Creek State Forest and includes infrastructure for substation platform extension, electrical equipment installation, access roads, bulk earthworks, drainage modifications, helicopter landing platform relocation, transmission line cut-in assets and a 50-metre bushfire buffer zone.

Construction activities will include site preparation involving vegetation clearing, topsoil stripping and stockpiling, and fencing installation.

The main construction phase encompasses bulk civil earthworks and concrete benching, followed by mechanical and electrical installation of prefabricated equipment, including inverters, transformers and overhead transmission lines.

Site rehabilitation of temporary construction areas will complete the project scope.

The substation expansion supports the commercial framework established between Stanwell Corporation and Genex Power through their 15-year power purchase agreement for the 775MW Bulli Creek Solar Farm.

Project planners have designed the expansion to avoid areas with Matters of National Environmental Significance value where practical. Due to the utilisation of previously disturbed areas, direct and indirect environmental impacts are considered minimal.

The substation expansion, which has a typical operational lifespan of 50 years, will provide long-term transmission capacity for renewable energy delivery from the Western Downs region.

Genex Power’s Bulli Creek Clean Energy Park

The 775MW Bulli Creek Solar Farm represents the first stage of Genex Power’s ambitious Bulli Creek Clean Energy Park, a multi-stage development covering 5,000 hectares located 45km southwest of Millmerran and 125km southwest of Toowoomba in Queensland.

Once operational, Genex claims the facility will become Australia’s largest grid-connected solar PV power plant.

The installation will incorporate more than 1.5 million bifacial solar modules mounted on approximately 204,000 steel foundation piles across the expansive site. The electrical infrastructure includes 232 integrated power skids, each rated at 4.2 MVA, and incorporates inverters, medium-voltage transformers, and MV switchgear to convert and condition the DC power generated by the solar arrays.

The Bulli Creek Clean Energy Park features a phased development approach, with the 775MW solar PV power plant designated as Stage 1. Future expansion plans include a battery energy storage system (Stage 2) with a capacity of 400MW to 600MW and a storage duration of 1,600MWh to 2,400MWh.

The full development potential extends to 2GW of combined solar and storage capacity, positioning the site as a major renewable energy hub in Queensland’s Western Downs region.

Read Next

October 23, 2025
Spanish power electronics specialist Ingeteam has won a contract to supply inverters and control systems for European Energy Australia's 100MW Winton North solar-plus-storage project in northeast Victoria.
October 23, 2025
Queensland's rooftop solar systems have exceeded 5GW of output for the first time, marking a milestone in Australia's solar expansion.
October 22, 2025
US thin-film manufacturer First has revealed another transfer of its 45X manufacturing tax credits in a deal worth around US$750 million.
October 22, 2025
The Queensland government has launched the Social Licence in Renewable Energy Toolkit, providing local councils in Australia with resources to navigate renewable energy project engagement and community consultation processes.
Premium
October 21, 2025
PV Tech Premium spoke with academic and industry experts about the rising tide of cybersecurity concerns in Europe's solar energy sector.
October 21, 2025
Australia's solar-plus-storage sector gained momentum with 725MW of solar PV approvals advancing across New South Wales and Queensland.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 10, 2026
Frankfurt, Germany