Securing transmission key to SECI’s latest 3GW pan-India solar tender

Facebook
Twitter
LinkedIn
Reddit
Email
Most projects are likely to be set up in the resource rich states of Rajasthan and Madhya Pradesh. Credit: Tom Kenning

The Solar Energy Corporation of India (SECI) has tendered another 3GW of inter-state transmission system (ISTS)-connected solar projects to be set up anywhere in India, adding to the 2GW of similar projects tendered in January.

In the latest 3GW tender, the capacity to be auctioned will be split between 12 projects of 250MW each. Each individual bidder will be eligible for a minimum of one project (250MW) and a maximum of three projects (750MW).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

With 5GW of ISTS projects now up for grabs across the country, one of the main challenges for project development will lie around grid-connection and transmission bottlenecks, according to Mudit Jain, a consultant at Bridge to India.

Jain told PV Tech that most projects are likely to be set up in the resource-rich states of Rajasthan and Madhya Pradesh.

Developers will have to find suitable project sites that are close to Central Transmission Utility (CTU) substations, which connect to the ISTS, with available capacity to evacuate more power. The other option is to approach Power Grid for extension of transmission infrastructure, which has a gestation period of 12-18 months. 

Jain added: “Developers who have done the groundwork for finding a site where the existing CTU substation has spare transmission capacity will find it easier to compete in this bid. As the commissioning timeline is 15 months from the date of PPA signing, the developer will have to move very swiftly to complete the groundwork.”

Who will buy the power?

The responsibility lies with SECI to tie up the power off-take with respective distribution companies (Discoms). The request for proposal (RfP) document issued stated: “Power procured by SECI from the above projects has been provisioned to be sold to the different buying utilities of India. The details of buying utilities shall be intimated at a later date.”

Jain said that, with more such tenders, Discoms will have to face a decision on whether to focus on buying solar power from parks or solar farms built within their own state or buying solar power from other states via SECI. State Discoms with solar parks in their own regions are already mandated to procure a certain amount of power from those parks.

For the 3GW tender, bidders shall submit their bid by offering a single tariff for each project. SECI will sign 25-year power purchase agreements (PPAs) with the successful bidders and the project must be fully commissioned within 15 months of the effective date of the PPA.

The maximum tariff payable to the project developer is fixed at INR2.93/kWh (US$0.045) for 25 years. However, Jain said that the impending threats of safeguard and anti-dumping duties are posing a big challenge for developers with this ceiling tariff, given that they would cause project tariffs to increase if imposed.

Projects will be set up on a Build Own Operate (BOO) basis. Already commissioned projects cannot be considered under this RfS. However, projects under construction or projects not yet commissioned will be considered, if not already accepted under any other central or state schemes.

11GW floated

It’s worth noting that there is now around 11GW of solar capacity in India that has been announced for tendering, for which bids have yet to be submitted. Moreover, this number does not even include the 860MW tender in Karnataka which has been stayed due to a technical hitch affecting one player’s participation in the bid.

The newest tender also comes off the back of several media reports suggesting that between 2-3.5GW of solar tenders have been held up by the various uncertainties plaguing the industry already, which has seen a drop in interest from players in some instances. These uncertainties include a customs tax dispute and the on-going anti-dumping duty investigation.

A total of 5GW was due to be tendered this February as per the Ministry of New and Renewable Energy's (MNRE) major tendering announcement at the end of last year.

Read Next

September 4, 2025
India’s Goods and Services Tax (GST) Council, the joint forum of the Centre and States, has reduced the GST rate on renewable energy components from 12% to 5%. 
September 4, 2025
Indian solar manufacturer Waaree Energies has acquired a 64% equity stake in power transformer manufacturing company Kotsons.
September 3, 2025
India has added 2.8GW of rooftop solar in H1 2025, a 158% year-on-year surge from just 1.1GW in the same period last year.
September 1, 2025
The US International Trade Commission (ITC) has voted to continue the investigation on imported solar cells from India, Indonesia and Laos.
August 28, 2025
Indian solar manufacturing firm INA Solar has broken ground on its fourth 4.5GW cell production plant in Narmadapuram, Madhya Pradesh.
August 26, 2025
Jakson Engineers is investing over INR80 billion (US$912.5 million) to set up a 6GW integrated solar module, cell, and wafer plant.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines