Solar Millennium’s 150MW Kuraymat solar hybrid plant touts performance 8% over estimated target

Facebook
Twitter
LinkedIn
Reddit
Email

Solar Millennium has claimed that its Kuraymat, Egypt solar-thermal power plant, in operation since June, has been surpassing field performance by 8%. The parabolic trough technology hybrid plant holds an overall 150MW electric capacity and in addition to solar energy, uses natural gas to allow for 24-hour operation.

Solar Millennium’s subsidiary Flagsol provided the solar technology for the project in addition to providing the design, heat transfer fluid (HTF) system in the absorber pipes and delivery of the control unit for the project. Orascom Construction oversaw the installation and commissioning of the project and will partner with Flagsol to receive operation and maintenance support. The two companies will jointly operate the solar section of the power plant for two years before it is handed over to the owner.
 
“Cooperation with our Egyptian partner, Orascom, works so well that we have, thus, established a basis for further cooperation in the region. Currently, we and Orascom participate together in the tender process for Morocco's first solar-thermal power plant”, Klaas Rühmann, the Kuraymat project manager in charge at Flagsol, explains.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Over 100 technicians built 2,000 collector units with the completed Skal-ET collectors measuring over 19.6 feet in height. These were installed at the solar field in several 328ft long rows of parabolic troughs. All of the collectors for the project automatically and permanently track the sun with the site said to hold an average solar irradiation of over 2,400Kwh per square meter and year. The Kuraymat solar field uses more than 53,000 parabolic mirrors to produce solar electricity.

The company noted that that the total cost of the project was over €250 million with 30% of that figure attributed to the development of the solar field. However, the Global Environment Facility (GEF) subsidized the solar project with around US$50 million.

Read Next

October 9, 2026
Pan-African renewables developer Axian Energy has signed a power purchase agreement (PPA) with energy aggregator and trader Africa GreenCo in Zambia.
October 9, 2026
India’s MNRE issued the 12th revision of its Approved List of Models and Manufacturers (ALMM) List-II for solar PV cells on 8 October 2026.
October 9, 2026
Funds have been raised from private equity providers for two community solar developers that benefit several US states, in separate deals.
October 9, 2026
The IPP has begun the build phase of a new 420MW hybrid renewable energy park in Mohave County, Arizona, with completion due in 2028.
October 9, 2026
Dos Grados has agreed to acquire three PV solar projects in Spain from Akuo, with a combined installed capacity of more than 500MW.
October 9, 2026
Spanish IPP Grenergy has secured a US$457 million non-recourse senior financing for a 446MW Chilean solar-plus-storage portfolio.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events, Upcoming Webinars
October 21, 2026
2pm AEDT
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland