Solar Millennium’s 150MW Kuraymat solar hybrid plant touts performance 8% over estimated target

Facebook
Twitter
LinkedIn
Reddit
Email

Solar Millennium has claimed that its Kuraymat, Egypt solar-thermal power plant, in operation since June, has been surpassing field performance by 8%. The parabolic trough technology hybrid plant holds an overall 150MW electric capacity and in addition to solar energy, uses natural gas to allow for 24-hour operation.

Solar Millennium’s subsidiary Flagsol provided the solar technology for the project in addition to providing the design, heat transfer fluid (HTF) system in the absorber pipes and delivery of the control unit for the project. Orascom Construction oversaw the installation and commissioning of the project and will partner with Flagsol to receive operation and maintenance support. The two companies will jointly operate the solar section of the power plant for two years before it is handed over to the owner.
 
“Cooperation with our Egyptian partner, Orascom, works so well that we have, thus, established a basis for further cooperation in the region. Currently, we and Orascom participate together in the tender process for Morocco's first solar-thermal power plant”, Klaas Rühmann, the Kuraymat project manager in charge at Flagsol, explains.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Over 100 technicians built 2,000 collector units with the completed Skal-ET collectors measuring over 19.6 feet in height. These were installed at the solar field in several 328ft long rows of parabolic troughs. All of the collectors for the project automatically and permanently track the sun with the site said to hold an average solar irradiation of over 2,400Kwh per square meter and year. The Kuraymat solar field uses more than 53,000 parabolic mirrors to produce solar electricity.

The company noted that that the total cost of the project was over €250 million with 30% of that figure attributed to the development of the solar field. However, the Global Environment Facility (GEF) subsidized the solar project with around US$50 million.

Read Next

July 3, 2026
The Asian Development Bank (ADB) has approved a US$160 million loan to support the deployment of at least 310MW of new solar capacity in Bhutan.
July 3, 2026
Researchers have developed a predictive framework for 2D perovskite design to enable more efficient, stable solar cells.
July 3, 2026
The US is reportedly drafting a ban on Chinese solar inverters over concerns that they pose a risk to the grid.
July 3, 2026
The state of New York has reached 8GW of cumulative installed distributed solar PV, putting the state ahead of its 10GW target by 2030.
July 3, 2026
German solar PV generation has continued to grow in the first half of 2026, reaching a new all-time high of 43.2TWh.
July 3, 2026
Australia's utility-scale solar PV and wind assets generated a combined 4.73TWh in June, an 11% YoY increase, according to Rystad Energy.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye