US ROUND-UP: ContourGlobal powers its first US solar plant, Arevon closes financing on 430MW PV in Missouri

Facebook
Twitter
LinkedIn
Reddit
Email
Arevon Energy's Vikings solar-plus-storage project.
The US$500 million Kelso Solar Project is Arevon Energy’s first utility-scale renewable development in Missouri. Image: Arevon Energy.

During a week marked by significant developments in the US clean energy sector, ContourGlobal launched its 185 MWp BHS I solar plant in Colorado, Puget Sound Energy broke ground on its 142 MW Appaloosa Solar Project in Washington, Arevon secured US$250 million for its 430 MW Kelso Solar Project in Missouri, and Ameren Missouri announced plans to build a 250 MW PV plant. 

ContourGlobal powers 185 MWp solar PV facility in Colorado 

Independent power producer (IPP) ContourGlobal has inaugurated a 185MWp solar PV facility in Weld County, near the town of Severance, Colorado. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

This marks the first operational PV plant for the IPP in the US, which is also the first phase of the Black Hollow Sun project. The PV plant was originally developed by Hanwha Renewables and acquired by ContourGlobal earlier this year. The second phase of the project, BHS II, will add 139MWp and is slated for completion by end of 2026. Together, the two phases will form the ‘largest PV installation in Northern Colorado’, delivering 324MWp of capacity, according to the IPP. 

The facility will supply power to Platte River Power Authority, which serves the municipalities of Fort Collins, Loveland, Estes Park and Longmont.  

Solar manufacturer Qcells supplied US-made modules and also provided engineering, procurement, and construction (EPC) services for the project. The completion of BHS I adds 185MWp of renewable capacity to the company’s US portfolio, bringing its total operating, under-construction, and late-stage development capacity to 2.8GW. ContourGlobal operates 5.3GW across 18 countries in the Americas, Europe, Africa and Asia.

Arevon Energy secures US$250 million tax equity for 430 MW Kelso PV project in Missouri

IPP Arevon Energy has secured a US$250 million tax equity commitment from Wells Fargo for its two-phase, 430MWdc Kelso Solar Project in Scott County, Missouri.

The US$500 million Kelso Solar Project is Arevon Energy’s first utility-scale renewable development in the state of Missouri. Arevon will own and operate the project, with phase one expected to reach commercial operations by the end of 2025 and phase two in the first quarter of 2026. Construction is creating approximately 450 jobs and supporting local businesses, including area stores, hotels, and restaurants. 

The deal brings Arevon’s solar and energy storage financings to US$4.5 billion over the past two years. Wells Fargo served as the tax equity investor, with legal support from Amis, Patel & Brewer, Stoel Rives, Sheppard Mullin, Husch Blackwell, and BCLP.  

Beyond Kelso 1 & 2, Arevon is expanding its Midwest portfolio, with two solar projects under construction in Indiana, Big Muddy Solar in Illinois set to start soon, and other renewable developments in progress. The company recently brought 480 MW of solar online, successfully integrating the projects into local communities.  

Arevon Energy, headquartered in Scottsdale, Arizona owns and operates 5.3GW of solar and energy storage across 17 states, representing over US$10 billion in investment. The company is constructing an additional 1GW, has developed 480MW of community-integrated solar with local utilities. 

Puget Sound Energy breaks ground on 142 MW solar project in Washington 

US utility Puget Sound Energy (PSE) has broken ground on its 142MW Appaloosa Solar Project, a utility-scale facility in the state of Washington. 

Part of the project will be co-located within PSE’s Lower Snake River Wind Facility in Garfield County. Appaloosa Solar is expected to supply 4% of PSE’s 2030 clean energy target and support summer peak demand.  

Qcells will supply modules for the project and provide EPC services. Commercial operation of the PV plant is expected by the end of 2026. The project will create around 300 construction jobs and engage local and diverse suppliers to support regional economic development. 

Since Washington state’s Clean Energy Transformation Act (CETA) passage in 2019, PSE has added over 6,000MW of renewable capacity, including 2,033MW from 11 new projects built to serve its customers’ energy needs. 

Ameren Missouri plans 250 MW solar Reform Renewable Energy Center 

US renewable energy developer Ameren Missouri, a subsidiary of Ameren Corporation, has planned to develop a 250 MW PV plant.

Planned next to Ameren’s Callaway Nuclear Energy Center in central Missouri, the 250 MW solar facility – called Reform Renewable Energy Center – will begin construction next year (pending approval) and is expected to come online in 2028. 

According to the firm, the site could accommodate up to 250 MW of energy storage, with Ameren Missouri potentially seeking Public Service Commissions (PSC) approval to install batteries to store excess solar output and release it during peak demand. Ameren Missouri owns the site and transmission interconnection, helping to cut construction time and costs. 

Mark Birk, chairman and president of Ameren Missouri, said: “Reform will also help us meet our goal of a balanced energy mix of about 70% from on-demand and 30% from intermittent sources, which allows us to achieve the two things our customers find most valuable: reliability and affordability.” 

Alongside Reform, Ameren Missouri is advancing multiple projects to boost long-term reliability. Castle Bluff Energy Center will provide peak-demand backup in 2027, while the Big Hollow Energy Center – the company’s first hybrid natural gas and battery facility – is slated for 2028, pending approval. Four solar projects totalling 400MW are under construction for service by end of 2026, joining three sites completed in 2024.

16 June 2026
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 16-17 June 2026, will be our fifth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2028 and beyond.
13 October 2026
San Francisco Bay Area, USA
PV Tech has been running an annual PV CellTech Conference since 2016. PV CellTech USA, on 13-14 October 2026 is our fourth PV CellTech conference dedicated to solar manufacturing in the USA. From polysilicon, wafers, ingots, cells and modules, to critical component suppliers including glass and frames, the event connects every stage of the value chain under one roof. PV CellTech USA also brings together investors, innovators, manufacturers and industry stakeholders to collaborate and strengthen domestic solar manufacturing across the United States.

Read Next

Premium
June 4, 2026
Global Solar Council CEO Sonia Dunlop highlights the pressing need for concerted action to prepare for the coming wave of PV decommissioning and help the industry achieve its goal of circularity.
June 4, 2026
Levanta and ib vogt have secured finance for projects and ACWA Power has leased 500 hectares for its own project.
June 4, 2026
The solar industry’s readiness for an expected surge in end-of-life PV projects and equipment is the subject of a special report that leads issue 45 of PV Tech Power, out now.
June 4, 2026
As solar imports to the US face increasing restrictions, domestic manufacturers are racing to build upstream production capability. With 66GW of module capacity chasing just 11GW of domestic cells, the supply chain crunch is reaching a critical inflection point, write Moustafa Ramadan and Joe Hennessy.
June 4, 2026
US-based solar manufacturer Thornova Solar has signed a strategic cooperation agreement with PV solutions provider Nextpower to incorporate steel frames into certain modules.
Premium
June 3, 2026
The UK renewable energy investment landscape is 'quite good', according to Anastasios Christakis, COO at Queequeg Renewables.

Upcoming Events

Solar Media Events
June 16, 2026
Napa, USA
Media Partners, Solar Media Events
June 30, 2026
Sacramento, California
Media Partners, Solar Media Events
August 25, 2026
São Paulo, Brazil
Media Partners, Solar Media Events
September 1, 2026
Mexico City, Mexico
Media Partners, Solar Media Events
September 9, 2026