WorleyParsons: Oregon battery EPC deal kicks off wave of distributed energy projects

April 17, 2018
Facebook
Twitter
LinkedIn
Reddit
Email
Eugene Water & Electric Board (EWEB) offers incentives to go solar, with average residential rooftop PV systems at around 2.4kW capacity each. Image: EWEB.

Australia-headquartered engineering and professional services company WorleyParsons said its first engineering, procurement and construction (EPC) contract for a battery storage project in the US shows how the energy sector is moving from “mega projects” to “portfolios of smaller projects”.

Australian Stock Exchange-listed WorleyParsons has dozens of offices around the globe and has been acquiring like-minded companies internationally since the early 2000s. Earlier this month, it was awarded an EPC contract for a 500kW / 1000kWh battery energy storage system in Oregon, USA.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

To be built at Howard Elementary School in the city of Eugene, the EPC provider was awarded a contract by Eugene Water & Electric Board (EWEB), a customer-owned utility in the mid-Western state. Construction begins in June, with commissioning by the end of September this year. As with other energy storage projects delivered for schools, communities and public sector buildings in much of the US, the system will both help reduce energy costs and add backup power in the event of outages. This will include adding the capability to use the battery in conjunction with solar PV to provide clean drinking water for Eugene residents in emergency or disaster situations, from a well that the Water Board wants to install in future at the school. It's the latest C&I or community storage project to be delivered to the US schools sector, with other recent projects including the deployment of Sharp SmartStorage systems at several schools in California by Jigar Shah's Generate Capital

To read the full story, visit Energy-Storage.News.

Read Next

January 27, 2026
Australia’s federal government has released a consultation paper detailing information on the proposed Solar Sharer Offer (SSO). 
January 22, 2026
The fundamentals of the global solar PV market will remain strong in 2026 despite the challenges the sector faced in 2025, according to new analysis from Wood Mackenzie.
January 22, 2026
Greek developer Metlen Energy and Metals has partnered with local maritime firm Tsakos Group to build a 251.9MW solar-plus-storage project in Greece.
January 22, 2026
New solar PV installations in Italy have reached 6.4GW in 2025, according to the latest data from transmission system operator Terna.
January 22, 2026
Green Gold Energy’s Morgan Solar Farm in South Australia has reached a key grid-connection milestone, having received its Section 5.3.4 letter under the National Electricity Rules (NER). 
January 21, 2026
Bellevue Gold has claimed to have set a new benchmark for off-grid renewable energy performance at one of its gold mines.

Upcoming Events

Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA