Delays, disputes and elections to slow India solar growth, predict analysts

February 26, 2014
Facebook
Twitter
LinkedIn
Reddit
Email

Analysts have predicted slow growth for India’s solar market this year due to delays in implementing its waning national solar mission.

The national solar mission (JNNSM) in India has a target for 1.1GW to be installed during the fiscal year 2013-14, and an overall target for 20GW by 2022.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Solar analyst, Bridge to India has compared installations globally to find JNNSM lacking. Globally, 39GW was installed in 2013, China installed 12GW last year with a national target of 35GW by 2015. Japan and the US installed 4GW last year.

Bridge to India also predicts a lacklustre year due to State solar policy and a slow start for the JNNSM’s phase II.

The JNNSM phase II draft was released in December 2012, but final calls for bids were not until a year later, December 2013 – PPA signings have also been delayed.

Energy market research firm, Mercom Capital Group predicts 1GW to be installed in India for 2014 – stagnant with 1,004MW installed in 2013, and 986MW in 2012.

Mercom predicts slow growth as no national solar projects are to come online until mid 2015 and “CSP projects have stalled” adding State solar policies are “all over the map”, as India also becomes a hotbed for a bubbling trade dispute with the US.

Mercom said “difficulties with project economic viability stemming from reverse auctions that have pushed down project margins”, the lack of implementation for a Renewable Purchase Obligation, and a national election on the way, are causing tremors in India’s solar market.

However in light of rising diesel prices, Raj Prabhu, CEO and co-founder of Mercom Capital Group said the solar market in India “looks better and better every day”, adding that “the case for solar in India will remain strong as long as the relevant policy goals address power shortages that affect millions of Indians, businesses, industries and agriculture,” said Prabhu.

The mandatory domestic content requirement is one policy that is being debated as earlier this week, the Indian government revealed the financial bid results for its auction for 750MW of solar energy, as part of JNNSM Phase II, with trade disputing US firm, First Solar missing out.

First Solar has previously dominated India’s thin-film market via a loophole in previous JNNSM bids, now closed, which did not include thin-film modules under the domestic content requirement (DCR). The company has worked with the US Export-Import Bank on a number of projects in India.

In September 2013, solar energy consultant, Bridge to India, published its solar ‘industry map’, revealing 42% of modules used in India are thin-film modules, with US-based First Solar taking the highest market share and Canadian Solar the highest of crystalline silicon modules.

In August 2012 local sustainability think-tank the Centre for Science and Environment (CSE) accused US thin-film manufacturers of exploiting the DCR “loop hole” to “ruin” the Indian domestic PV industry. CSE researchers claimed 80% of India’s manufacturing capacity was in disarray, forced to close or seek debt restructuring as a result.

The US filed a complaint to the World Trade Organisation earlier this month claiming that it should have equal access to India's procurement round. 

On the subject of the impact of the US trade dispute, Bridge to India analyst Jasmeet Khurana previously said First Solar had missed out “only based on the bid submitted by them. There are no political considerations. India is not that investment unfriendly”.

Read Next

April 7, 2026
Federal permitting delays have held up 11GW of new renewable energy deployment in the US in the last year alone, according to Crux.
April 7, 2026
The PPC Group has completed construction of a 2.13GW solar PV portfolio in Greece, which it described as the "largest" cluster in Europe.
April 7, 2026
Sangam Solar One, a subsidiary of Indian solar PV manufacturer Waaree Energies, has commissioned a 3GW PV module manufacturing facility in Samakhiali, Kutch, Gujarat.
April 7, 2026
US independent power producer (IPP) Geronimo Power has begun operations at a 117MW solar PV project in Ohio.
April 7, 2026
According to Ember, solar-plus-storage could supply up to 90% of India’s electricity demand at a levelised cost of electricity (LCOE) of INR5.06/kWh (US$56/MWh).
April 7, 2026
South Korea has announced plans to almost triple its operational renewable energy capacity from 37GW today to 100GW by the end of the decade.

Upcoming Events

Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland