Frontier Energy appoints Monford as EPC contractor for 132MW solar-plus-storage project in Western Australia

Facebook
Twitter
LinkedIn
Reddit
Email
Frontier Energy’s Waroona Renewable Energy Project will be developed across multiple stages. Image: Frontier Energy.

Frontier Energy has appointed Western Australian renewable energy contractor Monford Group as the fixed-price engineering, procurement and construction (EPC) contractor for the 132MWdc stage one of its Waroona Renewable Energy Project.

The deal also sees Monford agreeing to take AU$5 million (US$3.5 million) of its contract value in ASX-listed developer Frontier’s shares.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The appointment follows the completion of an Early Contractor Involvement process that allowed both parties to refine the scope and design of the 132MWdc solar and 81.5MW/562MWh battery energy storage facility before formalising the contract.

Monford has commenced detailed design and mobilisation preparations under an interim agreement, with full site mobilisation scheduled for September 2026. The EPC scope extends through commissioning and delivery of a fully grid-connected solar-plus-storage facility, with first generation targeted in the second half of 2028.

In lieu of AU$5 million in cash, Monford has been granted an option to acquire 25 million ordinary shares in Frontier at an exercise price of zero. Frontier executive chairman Jamie Cullen said the arrangement reflected strong alignment of interests.

“The agreement for Monford to receive AU$5 million of the contract value in Frontier equity provides strong alignment of interests and is a positive endorsement of the quality and long-term potential of the Waroona Project,” he said.

Monford CEO Ciaran Shannon said the project reinforced the company’s position as a leading contractor in the Australian renewable energy sector.

“Our participation as a shareholder aligns us with the long-term success of the project and demonstrates our confidence in Frontier’s vision and growth strategy,” Shannon said.

As noted by Frontier Energy in the announcement, Monford’s prior delivery of the Cunderdin 128MWdc solar and 55MW 4-hour duration battery energy storage system (BESS) project, another hybrid facility connected to Western Australia’s South West Interconnected System (SWIS) and similar in configuration to Waroona stage one, was particularly relevant to the appointment.

A fully funded project ready to build

The EPC appointment follows Frontier receiving credit-approved commitments for project finance debt facilities of up to AU$280 million from Natixis CIB and Sumitomo Mitsui Banking Corporation, announced on 17 July.

The package includes a construction and term facility of up to AU$250 million, a bank guarantee facility of up to AU$13 million, and a debt service reserve facility of up to AU$17 million, all of which qualify under the Green Loan Principles.

Combined with the AU$110 million conditional equity placement secured in June 2026, which received shareholder approval on 10 July, the project is now expected to be fully funded through construction and commissioning.

Settlement of the equity placement, at AU$0.20 per share across 550 million new shares, was scheduled for 21 July 2026.

In parallel with Monford’s early works, Frontier has progressed Western Power tendering for interconnection works, commenced substation EPC activities with Global Power Services, and placed long-lead orders for the main transformer and substation equipment.

The Waroona project has followed a long development path. Frontier assembled the site through the acquisition of Waroona Energy in late 2023, forming a combined 335MW solar portfolio.

As previously reported, the project was temporarily halted in October 2024 after Frontier failed to secure Reserve Capacity Credits from AEMO, which had been expected to underpin up to AU$27 million in annual revenue during the project’s first five years, requiring a restructure of the project’s financing and revenue assumptions.

The solar capacity subsequently grew from 120MW to 132MW through the adoption of higher-efficiency 660W modules, up from 610W. At the same time, the battery storage system was expanded to 562 MWh to meet a minimum 6-hour BESS requirement under Western Australia’s reserve capacity framework.

Frontier has outlined a multi-stage expansion at Waroona to approximately 1GW of solar generation and 660MW of battery storage by 2031, with stage two, which already holds development approval at approximately 120MW solar and 80MW of storage, expected to advance its definitive feasibility study during 2026 using part of the AU$110 million equity proceeds.

The site’s position 0.5km from the existing Landwehr Terminal substation removes the need for major new transmission infrastructure to support the multi-stage buildout.

2 February 2027
London, UK
Returning in 2027 for its 14th edition, Solar & Storage Finance Europe will bring together the brightest minds representing funds, banks, developers, utilities, government and industry across Europe and the UK on a programme that is solutions-focused from top to tail. The event is designed to enable leaders at the forefront of solar and storage investment and deployment in Europe to scale, learn and land themselves industry defining partnerships.

Read Next

August 10, 2026
Purvah Green Power has agreed to acquire six SPVs holding a combined 1.4GW of operational renewable energy capacity from ReNew Solar Power.
August 10, 2026
India’s SECI awarded 1GW to seven bidders under its RTC-TM tender, with Juniper securing the largest allocation.
August 10, 2026
US installer Sunrun has reversed recent declines in PV and energy storage installations in the second quarter of 2026, but trimmed its forecasts for the year.
August 10, 2026
Levanta Renewables has started construction at its Barotac Viejo solar-plus-storage project in the Philippines.
August 10, 2026
News of two solar project developments in Poland, where Orlen acquired a 216MW hybrid project and Enefit Polska inaugurated a 45MW site.
August 10, 2026
ABO Energy has agreed to sell its Hungarian and Polish subsidiaries, including projects, solar assets and 38 employees, to PPC.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye