Delays hit 50% of India’s state-tendered solar projects that were due last year

January 27, 2016
Facebook
Twitter
LinkedIn
Reddit
Email
Sever delays were reported from Telangana's allocations last year. Credit: Yogendra

Developers in India have failed to install 680MW of solar PV projects that were due to be commissioned by December 2015 because of project delays, according to consultancy firm Bridge to India.

Jyoti Gulia, senior manager, market intelligence, at Bridge to India, told PV Tech, that out of 1,485MW of allotted capacity under state tenders from October 2011 to September 2014, whose expected commissioning deadline was December 2015, nearly 50% has been delayed or partially lost for various reasons.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Furthermore out of this 680MW, Bridge to India expects almost 10% of the capacity to be completely stalled.

Capacity allotted vs actually commissioned. Credit: Bridge to India Project Database

Gulia added: “Clearly 50% is a big number and if this trend continues then the government will surely fall short of its targets.”

In a blog for PV Tech, Jyoti Gulia analyzes the project delays and problems ahead in 2016 in terms of transmission infrastructure and financing.

Read Next

April 10, 2026
India has become the third-largest country by installed renewable energy capacity, reaching 274.68, with over 150GW of solar PV capacity, according to statistics from the Ministry of New and Renewable Energy (MNRE).
Premium
April 10, 2026
Despite PV’s maturity, a new paper argues that its growing global significance makes ongoing research essential.
April 8, 2026
PV manufacturing capital expenditure is expected to rebound this year, following two years in the doldrums as the industry weathered a global oversupply of modules, new figures show.
Premium
April 8, 2026
After a sharp decline in 2023, PV manufacturing capital expenditure is set to bounce back this year, and not just in China, writes Moustafa Ramadan.
April 7, 2026
Sangam Solar One, a subsidiary of Indian solar PV manufacturer Waaree Energies, has commissioned a 3GW PV module manufacturing facility in Samakhiali, Kutch, Gujarat.
April 7, 2026
According to Ember, solar-plus-storage could supply up to 90% of India’s electricity demand at a levelised cost of electricity (LCOE) of INR5.06/kWh (US$56/MWh).

Upcoming Events

Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland