Delays hit 50% of India’s state-tendered solar projects that were due last year

Facebook
Twitter
LinkedIn
Reddit
Email
Sever delays were reported from Telangana's allocations last year. Credit: Yogendra

Developers in India have failed to install 680MW of solar PV projects that were due to be commissioned by December 2015 because of project delays, according to consultancy firm Bridge to India.

Jyoti Gulia, senior manager, market intelligence, at Bridge to India, told PV Tech, that out of 1,485MW of allotted capacity under state tenders from October 2011 to September 2014, whose expected commissioning deadline was December 2015, nearly 50% has been delayed or partially lost for various reasons.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Furthermore out of this 680MW, Bridge to India expects almost 10% of the capacity to be completely stalled.

Capacity allotted vs actually commissioned. Credit: Bridge to India Project Database

Gulia added: “Clearly 50% is a big number and if this trend continues then the government will surely fall short of its targets.”

In a blog for PV Tech, Jyoti Gulia analyzes the project delays and problems ahead in 2016 in terms of transmission infrastructure and financing.

Read Next

July 10, 2026
The financing will support the Government of India’s PM Surya Ghar: Muft Bijli Yojana (PMSMGBY) initiative.
July 10, 2026
Australia and India have formalised a broadened energy partnership that spans renewable energy deployment, supply chain resilience, critical minerals, rooftop solar training and uranium exports.
July 9, 2026
India added approximately 26GW of solar capacity and 3GW of wind capacity during the first half of 2026, according to JMK Research. 
July 9, 2026
Premier Energies expects to begin construction of the first phase of its planned 10GW ingot and wafer manufacturing facility in Andhra Pradesh shortly.
July 9, 2026
India's power transmission sector is set for a multi-year investment cycle between FY2027 and FY2032, according to ICRA.
July 6, 2026
Vikram Solar has commissioned its new solar module manufacturing facility at Gangaikondan in the southern state of Tamil Nadu.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye