Dutch PV braces for fresh grid connection limits after ‘record’ 2019

Image credit: Paul van de Velde
Dutch PV players are to face yet more grid connection limits in 2020, with one of the major operators warning of spreading bottlenecks after a year of record solar additions.
Liander, one of the Netherlands’ largest network operators, said in recent days it will have to restrict project connection requests again in 2020, adding to curbs it had already announced in 2019.
In a statement last Friday, the group repeated a pledge to invest €882 million (US$972 million) in grid upgrades this year but warned that holding off requests will remain necessary.
Liander laid out a number of “orange scarcity areas” in the provinces of Friesland, Gelderland and Noord-Holland, where capacity is unavailable but solutions are being “investigated”.
In addition, the firm offered a list of “red scarcity areas” in the aforementioned provinces and three others, where bottlenecks are more serious and alleviation measures are not an option.
Energy projects submitting connection requests in these code-red areas will have to wait until the grid upgrades have had the time to materialise, Liander explained.
Europe's third PV installer grapples with congestion
For Dutch PV, the past few years have combined meteoric growth – at 2.5GW added in 2019, the country is now seen as the year’s third fastest European installer – with pressure from politicians.
The industry’s success reaping billions in state incentives and putting forward ever larger projects has triggered a clampdown from lawmakers, who worry over impacts on grid and land scarcity.
As it outlined the 2020 grid restrictions, Liander attributed the bottlenecks to the rapid rise of solar, together with data centers and other energy-intensive applicants including greenhouse farming.
Reviewing PV installation volumes for 2019, the grid operator found additions had grown at rates from 34% to 59% across all of the Dutch provinces it serves, describing it as a "record".
Where a PV plant can be commissioned within a year, grid upgrades can take five to eight years, Liander argued, adding: “The Netherlands is not geared to these developments.”
In the past, however, PV bodies have blamed the bottlenecks on grid operators themselves. Holland Solar has, for one, said Liander and others failed to anticipate how quickly green energy would grow.
See here to browse the list and map of areas where Liander will restrict grid connection requests
The prospects and challenges of solar's new era in Europe and beyond will take centre stage at Solar Media's Solar Finance & Investment Europe (London, 5-6 February) and Large Scale Solar Europe 2020 (Lisbon, on 31 March-1 April 2020).
Solar Finance & Investment Europe
Feb 03 - Feb 04, 2021
ONLINE
The business of solar is changing, as the industry scales up, technology, IT and new players to the market will add complexity. This sparks a host of opportunities such as co-location of solar and storage and the rise of unsubsidised solar projects as well as challenges which will question the very business model of European solar asset owners. Solar Finance & Investment Europe is the meeting place for institutional investors, sovereign wealth funds, solar, wind and storage funds and large energy buyers to do business.
Also read...
-
PROJECT ROUND-UP: NextEnergy adds 53.8MWp to portfolio, BayWa r.e. sells Malaysian solar
-
Energy fund manager Glennmont Partners acquired by Nuveen
-
COVID-19 has minimal impact on PPA prices in Europe and America
-
‘Historic’ agreement signed between Luxcara and BeGreen for 415MWp of Danish solar
-
BayWa r.e. completes two floating solar projects in the Netherlands
Comments