India sanctions benchmark costs for small-scale and rooftop solar

March 20, 2017
Facebook
Twitter
LinkedIn
Reddit
Email
The revised benchmark costs come into force as of today. Credit: The Climate Group

India has sanctioned the benchmark costs for grid-connected rooftop and small-scale solar PV plants for 2017/18, according to a Ministry of New and Renewable Energy (MNRE) release.

Vinay Rustagi, managing director at consultancy firm Bridge to India, told PV Tech: “These numbers are essentially used to decide how much subsidy to give to rooftop companies.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Subsidy is also based on [the] auction process in many cases but there are still some cases where it is given on reference costs, as determined in these orders.”

The revised benchmark costs come into force as of today.

Rooftop capacity Benchmark cost (INR/W)
up to 10kW 70
>10-100kWp 65
>100-500kWp 60

Combined with a 30% capital subsidy for rooftop solar (70% for special states), and a feed-in tariff in certain states, the agricultural and residential PV segments are expected reach an inflection point around 2019-20 and will significantly take off once operational issues around battery-based energy storage have been sorted, according to global analysis firm Crisil Research's January report.

Today, MNRE also brought into effect revised benchmark costs for various off-grid and decentralised technologies, including solar with battery banks:

PV plant Benchmark cost (INR/W)
>1kW-10kW (with battery bank @ 7.2VAh/W) 135
>1kW-10kW (with battery bank @ 3.6VAh/W) 108
>1kW-10kW (with battery bank @ 1.2VAh/W) 90

Mercom Capital Group has also reported that standalone solar projects with a combined capacity of 149MW have now been installed in India under its off-grid programme, known as DDUGJY. This programme has been lagging behind both the rooftop and utility-scale sectors ever since the overall 100GW solar was announced.

Mercom also reported that the government is planning a solar energy program for decentralized power loom units in India, offering financial assistance and capital subsidies. This is due to come into effect on 1 April this year. The aim is to address power shortage issues faced by the decentralized power loom units.

Power minister Piyush Goyal has also said that India is expected to hit 20GW solar within 15 months.

Read Next

December 1, 2025
The Indian Ministry of New and Renewable Energy (MNRE) has requested comments on the proposal to increase the solar PV module efficiency of the Approved List of Models and Manufacturers (ALMM).
November 26, 2025
Indian solar PV manufacturer Vikram Solar has started commercial operations at its 5GW Vallam module manufacturing facility in India.
November 26, 2025
India has added 11GW of solar PV capacity during the third quarter of 2025, according to a report from the Institute for Energy Economics and Financial Analysis (IEEFA).
November 25, 2025
ACME Platinum has signed a PPA with the Solar Energy Corporation of India (SECI) for a 200MW solar-plus storage project in India.
November 24, 2025
India’s Railway Energy Management Company (REMC) has awarded 1GW of contracts to supply the railway network with round-the-clock (RTC) renewable energy.
November 21, 2025
ib vogt has entered a strategic partnership with Ingka Investments for a 210MW solar project in Rajasthan, India.

Upcoming Events

Solar Media Events
December 2, 2025
Málaga, Spain
Upcoming Webinars
December 4, 2025
2pm GMT / 3pm CET
Upcoming Webinars
December 17, 2025
2pm GMT / 3pm CET
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas