MGE, We Energies to acquire remaining 150MW of Wisconsin PV project

Facebook
Twitter
LinkedIn
Reddit
Email
Once this acquisition is approved by regulators, this phase of the Badger Hollow Solar Farm would begin generating electricity in 2021. Image: Martin Abegglen / Flickr

Madison Gas and Electric (MGE) and We Energies have signed off on a new partnership to acquire the remaining 150MW of the Badger Hollow Solar Farm.

MGE and We Energies filed a joint application with the Public Service Commission of Wisconsin, with We Energies set to own 100MW of the project and MGE with the remaining 50MW. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Jeff Keebler, MGE chairman, president and CEO, said: “This addition of cost-effective solar energy will help MGE reach our goal of net-zero carbon electricity by the year 2050 while also helping us to manage long-term costs to our customers. This is yet another step in our active transition toward greater use of cleaner energy sources to serve our community.”

Kevin Fletcher, president and CEO – WEC Energy Group, the parent corporation of We Energies, added: “This is another significant step in our transition to a clean energy future. Along with the environmental benefits of solar energy, this purchase will lower costs to customers over the life of the project.”

Once this acquisition is approved by regulators, this phase of the Badger Hollow Solar Farm would begin generating electricity in 2021.

Back in May, MGE and Wisconsin Public Service (WPS), a subsidiary of WEC Energy Group, received regulatory approval to own a combined 150MW at Badger Hollow. MGE will own 50MW, while WPS will own 100MW of this first phase of the project. Commercial operation of this phase is expected by the end of 2020.

Badger Hollow will be developed in southwestern Wisconsin, in Iowa County, near the villages of Montfort and Cobb, about 12 miles west of Dodgeville. The 300MW project is being developed by Chicago-based Invenergy. 

Read Next

October 23, 2026
New Jersey representative Rob Menendez has introduced the Socket Full of Sunshine Act, the first federal-level bill to support plug-in solar.
October 23, 2026
Deriva Energy has announced the close of approximately US$540 million in financing for its 350MW Sullivan County Power Project.
October 22, 2026
NextEra Energy recorded a 9.7% increase in its net earnings in Q3 2026, with earnings up 9.5% in the nine months to date this year.
October 22, 2026
Kendall Sustainable Infrastructure (KSI) has started operating three community solar projects totalling 15.8MWdc across New York and Oregon.
October 21, 2026
Solar power generation facilities can be exposed to risks from the effects of hailstorms, snow and typhoons, according to kWh Analytics.
October 21, 2026
Pivot Energy has closed a US$500 million bilateral corporate credit facility to further solar PV and BESS deployments.

Upcoming Events

Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye