MGE, We Energies to acquire remaining 150MW of Wisconsin PV project

Facebook
Twitter
LinkedIn
Reddit
Email
Once this acquisition is approved by regulators, this phase of the Badger Hollow Solar Farm would begin generating electricity in 2021. Image: Martin Abegglen / Flickr

Madison Gas and Electric (MGE) and We Energies have signed off on a new partnership to acquire the remaining 150MW of the Badger Hollow Solar Farm.

MGE and We Energies filed a joint application with the Public Service Commission of Wisconsin, with We Energies set to own 100MW of the project and MGE with the remaining 50MW. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Jeff Keebler, MGE chairman, president and CEO, said: “This addition of cost-effective solar energy will help MGE reach our goal of net-zero carbon electricity by the year 2050 while also helping us to manage long-term costs to our customers. This is yet another step in our active transition toward greater use of cleaner energy sources to serve our community.”

Kevin Fletcher, president and CEO – WEC Energy Group, the parent corporation of We Energies, added: “This is another significant step in our transition to a clean energy future. Along with the environmental benefits of solar energy, this purchase will lower costs to customers over the life of the project.”

Once this acquisition is approved by regulators, this phase of the Badger Hollow Solar Farm would begin generating electricity in 2021.

Back in May, MGE and Wisconsin Public Service (WPS), a subsidiary of WEC Energy Group, received regulatory approval to own a combined 150MW at Badger Hollow. MGE will own 50MW, while WPS will own 100MW of this first phase of the project. Commercial operation of this phase is expected by the end of 2020.

Badger Hollow will be developed in southwestern Wisconsin, in Iowa County, near the villages of Montfort and Cobb, about 12 miles west of Dodgeville. The 300MW project is being developed by Chicago-based Invenergy. 

Read Next

October 9, 2026
Funds have been raised from private equity providers for two community solar developers that benefit several US states, in separate deals.
October 9, 2026
The IPP has begun the build phase of a new 420MW hybrid renewable energy park in Mohave County, Arizona, with completion due in 2028.
October 8, 2026
Toyo has held a ribbon-cutting ceremony to mark the expansion of its solar module manufacturing plant in Humble, Texas.
Premium
October 8, 2026
PV Talk: Indosol's Manoj Pothireddy tells PV Tech Premium that opportunities remain for overseas wafer manufacturers to export to the US.
October 7, 2026
Independent power producer (IPP) Zelestra has closed a US$350 million credit facility for the 203 MW Reclamation Solar project in Indiana.
October 7, 2026
US clean energy developer Clearway Energy has closed financing and started construction on a 650MW solar project in Missouri.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events, Upcoming Webinars
October 21, 2026
2pm AEDT
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland