Report: Slow, expensive nuclear no climate champion as PV costs drop

Facebook
Twitter
LinkedIn
Reddit
Email
A view of the Hinkley Point nuclear station from the west. Source: Roger Cornfoot, Creative Commons

The world is witnessing an “organic nuclear phaseout” partly precipitated by a drop in solar and wind costs, according to a new report that posits that nuclear power is too slow to build and too expensive to run to effectively fight climate change.

Utility-scale solar's levelised cost of electricity (LCOE) has dropped 88% in the last decade while the cost of nuclear has increased by 22%, according to the latest edition of the annual World Nuclear Industry Status Report (WNIS).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It is now cheaper, the analysis claims, to build and run new renewables than extend existing nuclear power plants. 

“You can spend a dollar, a euro, a forint or a ruble only once: The climate emergency requires that investment decisions must favour the cheapest and fastest response strategies. The nuclear power option has consistently turned out the most expensive and the slowest,” said WNIS project coordinator Michael Schneider.

Nuclear construction has shrunk over the past decade; there are 46 units currently under construction globally, a sharp drop from 234 in 1979. Only one new nuclear project has been inaugurated so far this year.

“The renewal rate of nuclear power plants is too slow to guarantee the survival of the technology. The world is experiencing an undeclared ‘organic’ nuclear phaseout,” Schneider claimed.

Further cost overruns for £92.50/MWh Hinkley Point

The WNIS analysis stresses that nuclear plants’ slow build rates are problematic at a time of pressing climate emergency. New nuclear plants take on average between five and 17 years longer to build than utility-scale solar or onshore wind, and the nine nuclear reactors fired up in 2018 took an average of 10.9 years to build.

This very week, EDF revealed its beleaguered Hinkley Point C nuclear project in Somerset, England, has seen overall costs creep up from the £19.5 billion (US$24 billion) outlined in 2010 to somewhere between £21.5 billion (US$26.5 billion) and £22.5 billion ($US27.8 billion) today.

Power from Hinkley Point C – which is running years behind schedule and is estimated to come online in 2025 or 2026 – was set at £92.50/MWh (US$114/MWh) in 2012. Meanwhile, prices for wind energy in the UK dropped to £40/MWh (US$49/MWh) on 20 September.

The report says that it is more environmentally advantageous to close and replace existing nuclear plants with new technologies than it is to keep them running.

“The closure of uneconomic reactors will not directly save carbon dixide emissions but can indirectly save more carbon dioxide than closing a coal-fired plant, if the nuclear plant’s larger saved operating costs are reinvested in efficiency or cheap modern renewables that in turn displace more fossil-fuelled generation,” the report reads.

It notes that in 2018, 165GW of renewables were added to the world’s power grids. Nearly 100GW of new solar capacity came online, a 13% increase from the year before, while nuclear power output inched forward by 9GW, a 2.4% increase.

Read Next

July 30, 2026
Origis Energy has built the first 1GW of solar PV capacity at its planned massive 2GW Rockhound solar-plus-storage facility in Texas.
July 30, 2026
EDPR has agreed to sell an 80% equity stake in a 384MW solar-plus-storage portfolio in the US to a Private equity firm Ares Infrastructure.
July 30, 2026
Walden has secured US$250 million from Crayhill Capital Management to support its 5GW US utility-scale solar PV and BESS pipeline.
July 30, 2026
Australia's CEC calls for a national ‘Renewable Resources Payment’ scheme, requiring a legislated payment for every MWh of renewables.
July 30, 2026
Renewables supplied 42.1% of electricity generated across Australia's NEM in the three months to June 2026, a new quarterly high for Q2.
July 29, 2026
ADB has approved an US$850 million loan to support the second phase of reforms for India's flagship residential rooftop solar programme.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye